A-MSASoADCfl CONSTRUCTON CO. iNC
April 14, 1998
Me. Kathy Giliberti
Silverstein Properties, Inc.
120 Broadway
New York. NY 10271
RE: Mayor's Office of Emergency Management
7 World Trade Center
Dear Ms. Giliberti;
We are pleased to submit herewith our proposal to perform the following work in accordance
with Generator Prepurchase Specifications dated March 20. 1998 as prepared by Cosentini
Associates, LLP as per the following breakdown for the sum of SEVEN HUNDRED
SEVENTEEN THOUSAND EIGHT HUNDRED NINETY DOLLARS ($717,890.00):
Atlantic Cooper Cummtne H.O. Penn Rudox
3-500 KW $688,489.00 $892,000.00 $733,000.00 $808,848.00 5855,700.00
Generator
Graphic 9,747.00 5,000.00 10.000.00 8,848.00 8,300.00
Annunciator
275 Gal. Day 3,467.00 3.850.00 6,500.00 3,650.00 3.800.00
Tank
Disassemble 18,458.00 included Included Included included
Reassemble
Rigging Included Included Included Included included
Subtotal $620,141.00 $700,850.00 $749,500.00 $819,346.00 $665,800.00
8% General $49,611.00 $58,068.00 $59,980.00 $49,548.00 $53,264.00
Conditions
6% Overhead/ $40,185.00 $45,415.00 $48,588.00 $40,134.00 $43,144.00
Fee
1.25% Insurance $8,874.00 $10,029.00 $10,725.00 $8,862.00 $9,528.00
$718,81100 I $812.362.00 $717.896.C^ $771,736.00
Total $868,753.00
Continued.../
317 MADISON AVENUE. NEW YORK, NY 10017, 212.922 1020. FAX 212 949 9782