Same-box records
Electrical and fuel line cost correspondence, 7 WTC, June 1998 · Box 7DCASNYC-WTC_000173102
Internal memo discussing cost quotes for electrical tapping fees and fuel line installation at 7 World Trade Center, including Silverstein's $302,410 fuel line cost and new…
1 shared topics · Same agency, volume and box · similarity 1.000
Correspondence regarding electricity plan review, June 1998 · Box 7DCASNYC-WTC_000173470
Letter discussing electrical issues and plan review requirements for the Mayor's Office of Emergency Management at 7 World Trade Center.
Same agency, volume and box · similarity 0.907
Letter re: electricity requirements, June 1998 · Box 7DCASNYC-WTC_000173242
Letter transmitting governing issues concerning electricity for the Mayor's Office of Emergency Management and noting tapping fee requirements.
Same agency, volume and box · similarity 0.906
Letter enclosing electricity requirements plan, June 12, 1998 · Box 7DCASNYC-WTC_000172128
Letter enclosing governing documents and plans regarding electricity requirements for the Mayor's Office of Emergency Management.
Same agency, volume and box · similarity 0.905
Revised budget with contingencies, 7 World Trade Center, 1998 · Box 7DCASNYC-WTC_000173426
Budget sheet showing total costs including furniture, moving contingencies, and LAN/computer expenses for the Mayor's OEM project.
1 shared topics · Same agency, volume and box · similarity 0.897
Construction cost estimate approval, 7 World Trade Center, July 1998 · Box 7DCASNYC-WTC_000173421
Memo summarizing reviewed documentation and approving revised trade cost estimates for the Mayor's Office of Emergency Management project.
1 shared topics · Same agency, volume and box · similarity 0.893
Correspondence regarding cost estimates for Mayor's OEM project, June 1998 · Box 7DCASNYC-WTC_000173149
A letter from the Division of Real Estate Service referencing original and revised cost estimates for renovation work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.892
Minutes of Consultant's Meeting #1: Shop drawing status, July 1998 · Box 7DCASNYC-WTC_000173789
Record of a meeting reviewing the status of HVAC and other shop drawings for the Mayor's Office of Emergency Management project.
1 shared topics · Same agency, volume and box · similarity 0.891
DCAS letter re: cost estimates, Mayor's OEM project, July 1, · Box 7DCASNYC-WTC_000173155
Letter from DCAS dated July 1, 1998, detailing original and revised cost estimates for the Mayor's Office renovation.
1 shared topics · Same agency, volume and box · similarity 0.891
DCAS letter on construction cost estimates, July 1998 · Box 7DCASNYC-WTC_000167308
Letter from DCAS reviewing and summarizing documentation for construction cost estimates for the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.890
Project cost summary with addenda and fees, 1998 · Box 7DCASNYC-WTC_000173113
Financial summary listing original bid, generator costs, electric tapping fees, and total project costs for a City facility upgrade.
1 shared topics · Same agency, volume and box · similarity 0.888
Construction budget summary, 7 World Trade Center, 1998 · Box 7DCASNYC-WTC_000173424
Financial sheet detailing bid prices, scope deductions, and revised costs for hurricane wall and bulletproof materials at the site.
1 shared topics · Same agency, volume and box · similarity 0.887