V. Scope of Services / Approach TKLP
8. Submission of Documents — TKLP will submit progressively the following documents
for approval before significant work is done on the next document;
a. Procedures Manual
b. Statement of Criteria
c. Space Study Drawings
d. Basis of Design
e. Opinion of Cost
Design Development
1. TKLP will review and comment on CDCSA's comments on TKLP's previous delivery.
2. Revise Basis of Design — TKLP will adjust the previously prepared the BODbased on
CDCSA's submission. TKLP will then layout the major distribution of the basis of design's
systems on the architectural floor plans. TKLP has assumed that the architect has gone
through a reliability analysis of their floor plan documents addressing compartmentation
of critical systems, avoidance of water damage, and hierarchy for security. TKLP will
develop space layouts formajorequipment rooms. Establish system distribution; prepare
details to determine shaft, ceiling space and general service areas for MEP systems.
3. Participation in Reliability Analysis—TKLP will make their project manager, mechanical
services engineer, electrical engineer, and security/fire alarm engineer available for two
days to attend this meeting.
4. Proj ect Budget — TKLP will prepare a construction cost budget based upon their design
development documents. This budget will be based upon historical square foot costs and
parameter costs, i.e. cost per ton or per KW. The construction cost budget will be broken
down by major disciplines following the CSI code of accounts and by function as pro
vided by CDCSA. This budget will be just an update, not a new one.
5. Value Engineering Study — TKLP's project director, project manager, mechanical ser
vices engineer, electrical chief engineer, and fire alarm/security engineer will meet to
gether to evaluate the design criteria, basis of design, and distribution documentation as
a value engineering study. Minutes will be taken of this meeting and each item identified
will include impact statements on operating costs, capital costs, risk of outage and repair
time.
6. TKLP will revise the design criteria document, the basis of design document and the
system distribution documents based upon a single design presentation with the client/
tenant/associated agency that will be attended by TKLP's project director, project man
ager, mechanical services engineer, electrical engineer, and security/fire alarm engineer.
Forest City Tech Place Associates for Full Engineering Services 05/06/92 (P237] V-3