TABLE 1
SUMMARY CHART OF FINDINGS
Total(6) Under Annual P.W. of Major Private Basic Parameters
Capital Pinning Maintenance Capital & Constr. Property App. Ave
Cost Cost Cost Maintenance Disruption Required Length Depth
Alternative ($1000) ($1000) ($1000) Cost (Y or N) (Y or N) FT FT
1 11,800 600 (1) 11,800 y(2) y(4) 4,200 13
2 8,000 1,200 8,000 y(3) y(4) 3,130 7
(1)
3 2,100 270 16.0 2,400 N N 150 30
4 12,?00 30.0 13,^0 y(5) N 4,900 14
(1) No additional maintenance cost; considered part of normal maintenance provided by DOS for gravity sewers.
(2) Potentially major disruptions to Convention Center Operations because to traffic disruption on 39th Street,
11th Avenue and 12th Avenue.
Possible disruptions to Lincoln Tunnel Operations
{3} Potentially major disruptions to Convention Center Operations because of traffic impacts along 34th Street, and 12th
Avenue at 34th Street.
(4) 2400 square feet in the Convention Center Plaza area
(5) Potentially major disruption to traffic along 10th Avenue amd 34th Street between lOth and 11th Avenues,
(6) Total capital cost includes cost of underpinning