DEP comments on drainage plans, Oct 1983 · Box DEP Box 44NYC-WTC_000165844
Department of Environmental Protection review comments on 30% plan drawings requesting key plans, legends, and distance measurements.
1 shared topics · Same agency, volume and box · similarity 0.958
DEP final design review comments, tunnel project, Jan 1988 · Box DEP Box 44NYC-WTC_000165322
Department of Environmental Protection letter providing design review comments on tunnel project contract drawings, requesting pressure relief manhole details, existing sewer…
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.957
DEP comments on WTC Dey St manhole load, March 1982 · Box DEP Box 44NYC-WTC_000165536
March 15, 1982 DEP letter providing engineering requirements for a telephone manhole load above the proposed 13-inch sewer line.
1 shared topics · Same agency, volume and box · similarity 0.957
Letter with comments on WTC tunnel drawings, January 1986 · Box DEP Box 44NYC-WTC_000165316
Department letter providing technical comments on final contract drawings for the WTC tunnel project.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.955
Hydraulic proportion charts for WTC sewer design · Box DEP Box 44NYC-WTC_000165522
Technical diagrams and tables showing proportions of value when flowing full for sewer design calculations related to the WTC project.
Same agency, volume and box · similarity 0.949
DEP comments on WTC Dey St sewer plans, March 15 · Box DEP Box 44NYC-WTC_000165584
Department letter providing specific engineering requirements for a telephone manhole load and sewer centerline location.
1 shared topics · Same agency, volume and box · similarity 0.949
NYC-WTC_000165345 · Box DEP Box 441 shared topics · Same agency, volume and box · similarity 0.948
DEP letter re tunnel project drawings, July 1987 · Box DEP Box 44NYC-WTC_000165377
Letter from DEP Bureau of Sewers regarding unreviseed drawings and as-built records for the tunnel project.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.948
General notes for drainage work specifications, 10th Ave Tunnel · Box DEP Box 44NYC-WTC_000165853
Contract notes specifying requirements for maintaining existing connections and restoring manholes during tunnel construction.
1 shared topics · Same agency, volume and box · similarity 0.945
DEP comments on sewer chamber structural computations, June 1984 · Box DEP Box 44NYC-WTC_000165790
Letter provides specific design comments regarding roof slab thickness and removable slab configuration requirements.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.944
DEP letter re: WTC Church Street underpass preliminary drawings · Box DEP Box 44NYC-WTC_000165544
July 28, 1983 DEP letter discussing comments on preliminary plans for the Church Street underpass and sewer support provisions.
Same agency, volume and box · similarity 0.944
DEP sewer chamber structural design comments, June 1984 · Box DEP Box 44NYC-WTC_000165786
Department of Environmental Protection memo reviewing structural computations for a proposed sewer chamber, providing specifications for roof slab thickness and steel values.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.943