WTC River Water Intake
System Relocations
24 hours notice thereof by the Contractor. Re
pair leaks which occur prior to the completion of
this Contract at once. Be responsible for any
damage caused by such leaks and repair thereof
and reimburse Contractor for all expense incurred
thereby. This Subcontractor indemnifies the Con
tractor against loss, liability, damage or ex
pense, including reasonable attorneys' fees, in
connection with any claim resulting from such
leaks.
1..15 UNIT PRICES
A. State and hold firm for the duration of the construc
tion contract, unit prices for the. following items.
Reflect in the unit price costs for the addition as
well as the deletion of each item including profit,
overhead, and insurance of each trade involved. Spe
cifically reflect in the unit price the final price of
the installed and operating item to the Owner? in full
accordance with plans, specifications and Contract
Documents. Prices shall include all labor, materials.
miscellaneous appurtenances, etc. for the complete
installation.
B. Unit Price No. 1: 66" 0 reinforced concrete pipe,
straight run, including pipe supports, per linear
foot.
C. Unit Price No. 2; 66" 0 steel lined, reinforced con
crete pipe at bends and transitions including all pipe
supports, per centerline linear foot.
D. Unit Price No. 3; 66" 0 pipe access manhole complete
With’ cover plate, frame, access ladder as detailed,
each.
E. Unit Price No. 4; 20" 0 prestressed concrete cylinder
pipe including pipe supports, per linear foot.
F. Unit Price No. 5; 20" 0 pipe access manhole complete
with cover plate, frame, access ladder as detailed,
each.
u• Unit Price No. 6: Concrete thrust block, per cubic
yard.
H. Unit Price No. 7; For alternate M-1, 66" 0 steel
pipe, concrete encased as detailed, per linear foot.
Mechanical
Special Conditions
15010-13
NYC-WTC_000165173