Batterj^ark City
Commercial Center Bldg. 'B'
WTC River Water Intake
System Relocations
E. Approval of any submitted data or shop drawings for
material, equipment apparatus, devices, arrangement
and layout shall not relieve Subcontractor from re
sponsibility of furnishing same of proper dimensions
and weight, capacities, sizes, quantity, quality and
installation details to efficiently perform the re
quirements and intent of the Contract. Such approval
shall not relieve the Subcontractor from responsibili
ty for errors, omissions or inadequacies of any sort
on submitted data or shop drawings.
F. Each shop drawing to contain job title and reference
to the applicable drawing and specification article.
G. Within fifteen (15). days after award of Contract, sub
mit for approval, a list of all material and equipment
manufacturers whose products are proposed, as well as
names of all Subcontractors whom this Trade proposes
to employ.
H. Within three (3) weeks after award of Contract, submit
a list of all shop drawings which will be submitted in
the course of the project. List to show disposition
of each item, including date of submission, approval,
and the like. List to be kept up-to-date throughout
entire construction period.
1. Submit shop drawings and manufacturer's data for the
following items in accordance with the Contract Docu
ments:
1. Coordinated, detailed shop layout drawings of all
services and distribution systems, including
plans, profiles and sections.
2c Location and size of related piles, concrete
platforms, manholes, and other foundations and
supports.
3. Schedule of pipe and fittings, materials and
application.
4- Details of piping supports, elbows, manholes con
nections to existing piping, anchors, thrust
blocks, and miscellaneous appurtenances.
5. Sacrificial anodes and cathodic protection.
Mechanical
Special Conditions
15010-11
NYC-WTC_000165171