■■ DEP Form409N
CONTRACT AND CONTRACT CHANGE NUMBER
Rem, of Rooftops/Facades in Vicinity of WTC - Area 3 Ch.1
COMPTROLLER'S REGISTRATION NUMBER
CT 826 20020015798
BUDGET LINE CONTRACT ID and DESCRIPTION
ROF-REM1 Remediation of Rooftops/Facades In Vicinity of WTC Area 3
CONTRACTOR'S NAME AND ADDRESS PIN FMS PROJECT ID
Trio Asbestos Removal Corp., 14-20 129'*’ Street, Collie Point, N.Y. 11356 826WTCROOF03 826_
CONTRACT AWARD AMOUNT DESIGN FIRM (if applicable)
$1,005,650.00 %
ITEM DESCRIPTION OF WORK CONTRACTOR'S AUTHORIZED
NUMBER ATTACH ADDITIONAL SHEETS IF NECESSARY PROPOSAL COST
1 Additional remediation of building roofs, setbacks and/or
building facades within the vicinity of the World Trade Center
under the same terms and conditions set forth in the contract.
The additional square footage of areas identified to be cleaned
is estimated to be the sq. ft.
The time period of perfomance for this contract requires an
extension to October 31, 2002 for an additional 36 consecutive
calendar days.
TOTAL= lnterim(if any) or Forced (if any) PLUS Finai (if any) or $ $
Revised (if any) otherwise TOTAL = This Change Order
PREVIOUS AMOUNT REGISTERED FOR THIS CHANGE (if any) $
AMOUNT REQUIRED FOR REGISTRATION OF THIS CHANGE $
1. The Contractor shall sign 4 copies of this form, and together with 4 copies of the Contractor's detailed cost proposal, send It to the Agency
Contact for this Contract within seven calendar days of receipt of this proposed contract change.
2. If the total amount of the extra work (excluding credit change orders) issued for the contract exceeds 10% of the contract amount or $100,000,
whichever Is greater, or exceeds previous BOE/ODC/MOC Approvals, the Agency must obtain approval from the Mayor's Office of Construction
or the Mayor's Office of Contracts (as applicable) In order to award extra work.
3. When a price Is agreed to between the Commissioner's authorized representative and the Contractor, and all required approvals have been
obtained, the Contractor shall be issued a contract change to proceed with the work. Contractor shall not proceed with this work until Issued a
contract change or otherwise directed by the Commissioner.
4. Any payments for extra work must be requisitioned separately from payments for work required under the original contract
5. All Construction and Construction-Related work Is subject to post-audit by the Department's Engineering Audit Officer and the Comptroller's
Chief Enaineer. -
Rev 11/24/00 DEPFM409N