From: Smyth, Virginia
Sent: Tuesday, April 15, 2003 10:39 AM
To: Giisenan, Michael
Subject: FW: WTC Contract Status
???
—Original Message—
From: Terradano, Joe
Sent: Tuesday, April 15, 2003 10:27 AM
To: Smyth, Virginia
Subject: RE: WTC Contract Status
Virginia,
Thanks, a reminder FEMA has informed the city that all payments must be made by 4-30-03 (not work done) for us to get
reimbursed, this includes the interior work, they are in negotiations with the city to reallocate the unspent monies, but there
has been no indication on how that is going.
JoeT
—Original Message—
From: Smyth, Virginia
Sent: Monday, April 14, 2003 4:14 PM
To: Terradano, Joe
Cc: Golin, Beverly; Giisenan, Michael
Subject: WTC Contract Status
Attached is another copy of the status of the current WTC contracts. As per my conversation with Beverly this
morning, all work under the Exterior Cleaning Contracts is complete. Two contractors, Kurzban and Trio have
received final payments. The other two remaining just ended on March 31st. Fiber Control requires a change order in
the amount of $87,812 in order to finalize payment (Total will be $2,578,240) and we are waiting for a final invoice from
Warren & Panzer.
The air monitoring contracts with JLC (20020014002) was finalized at a total of $331,500; and Riverpoint
(20020010450) was finalized at $348,840.
The final WTC payment for Pednault (20010021151) is currently being processed for $165,963. The contract is
multiyear and will continue providing regular laboratory services.
If you have any questions, please let me know.