Work progress status report, cleaning and removal, Mar 2003

Machine-extracted title · confidence 85%

Contractor progress report noting wall and ceiling removal near completion with ongoing general cleaning operations.

NYC-WTC_000163070–000163071

Folder label: “E-mails 2003 M. Gilsenan

Page image
Scanned page image, NYC-WTC_000163070
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

GilSenan, Michael From: Dave Stanke [[email protected] ] Sent: Tuesday, March 18. 2003 9:50 AM To: Theodorellys, Penny; [email protected] Cc: Radhakrishnan, Krish; Gilsenan, Michael Subject: RE: Can we have an update? How's it going?

Penny, That is all I was looking for I've had positive reports from Chris, but I also like to hear your perspective to be sure nothing is amiss. If there are any issues that need my attention, please contact me at any time.

Thanks again for your efforts.

Dave

---- Original Message---- From: Theodorellys, Penny [mailto:[email protected] ] Sent: Tuesday, March 18, 2003 8:34 AM To: Dave Stanke; [email protected] Cc: Radhakrishnan, Krish; Gilsenan, Michael Subject: RE: Can we have an update? How's it going?

Work is progressing on schedule. DEP has been inspecting the work daily and has been addressing issues as they arise. The USEPA is being forwarded all sampling results and is receiving updates.

Chris Warnick inspected the work progress last week. I received a positive report. I will be contacting him again in the next couple of days to arrange another walk through.

The removal of walls and ceilings is mostly complete.The removal of the ducting is still in progress but also almost done. Of course, general cleaning has been occurring simultaneously to keep the areas free of debris.

The schedule as per the most recent submittal by ETS is building opening at 6:30 a.m. to 1:00 a.m. The work shift is 7:00a.m. to 12:30 a.m. The visual inspections are tentatively scheduled for next Monday with clearance testing to follow.

Basically, I won't have any substantive updates until we are closer to the project's end. Feel free to contact me with any questions.

---- Original Message---- From: Dave Stanke [mailto:[email protected]] Sent: Tuesday, March 18, 2003 12:06 AM To: [email protected] Subject: Can we have an update? How's it going?

Penny, Can you provide us with an update? How is the work proceeding? Any changes to plans or schedules?

Thanks, Dave

1

NYC-WTC_000163070

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000163070Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →