December 17, 2002 114 LIBERTY STREET
REMOVAL OF DUST, DEBRIS, AND CONTAMINATED MATERIALS
c. A schedule of equipment to be used including numbers and types of all major
equipment such as HEPA - vacuums.
2. A written, detailed, job-specific plan of the procedures proposed for use in complying
with the requirements of this specification. The plan shall include the following:
a. Location and layout of decontamination areas;
b. Location and layout of all negative air units and the HEPA filtered window
mounted manifolds used for make-up air, as well as all calculations performed to
verify that it meets the ventilation requirements of these specifications.
c. The sequencing of contaminated dust, debris and material removal work;
d. The interface of trades involved in the performance of the work;
e. Methods to be used to assure the safety of building occupants and visitors to the
work site.
3. Description of protective clothing and approved respirators to be used, including make,
model, and NIOSH approval numbers.
4. List of workers (chain-of-command).
5. Delineation of the responsibility of work site supervisory personnel, their names,
resumes, pager numbers and home telephone numbers.
6. Explanation of decontamination sequence and isolation techniques for the Work Area.
7. Description of any prepared methods, procedures, techniques, or equipment other than
those specified in the Contract Documents.
8. Description of the final clean-up procedures to be used.
9. Written description of emergency procedures to be followed in case of injury or fire. This
section must include evacuation procedures, source of medical assistance (name and
telephone number) and procedures to be used for access by medical personnel
(examples: first aid squad and physician).
NOTE: Necessary Emergency Procedures Shall Take Priority Over All Other
Requirements of These Specifications.
10. Product data and Material Safety Data Sheets (MSDS) for sealants, firestopping foam,
cleaners/disinfectants, spray adhesive, water-based strippable coatings and any and all
potentially hazardous materials that may be employed on the project in accordance with
the OSHA Hazard Communication Standard (29 CFR 1910.1200). No work involving the
aforementioned will be allowed to proceed until MSDS's are reviewed and approved by
the Owner. Include a separate attachment for each sheet indicating the specific worker
protective equipment proposed for use with the material(s) indicated.