Gilsenan, Michael
From: Theodorellys, Penny
Sent: Tuesday, April 01, 2003 9:40 AM
To: [email protected]
Cc: Radhakrishnan, Krish; Gilsenan, Michael
Subject: 114 Liberty Street
Chuck-
The asbestos air results received so far were forwarded over by fax. The contractor was
directed to re-clean 7*”, 8’^, 9^, and 10‘^ floors. I’ll send the additional results as I receive
them.
Let me know about any issues you may have with any of the results ASAP.
Have you received any of the dioxin results directly? I know you have been dealing with the
lab. I am still waiting on the pre-dioxin results.
The pizza shop on the first floor has a deteriorated, heavily damaged ceiling. The material has
40-50% amosite and the substrate contains chrysotile. We are going to have to clean the
area and leave it isolated from the remainder of the building. The 9* floor asbestos results are
higher than the other floors received to date. The 9”’ floor has a pipe chase with in-place
insulation (the material is damaged). A tent was constructed around the material prior to
clearances. The architect was notified that the material would have to be addressed. As
noted above, we are having the apartment re-cleaned. —Just wanted to keep you in the loop
of information.
Keep in touch (718) 595-3657 or cell (917) 769-1029. Thanks again for all your help.
Penny