The interpretation of these results is constrained by the scientific
uncertainty regarding the potential for the measured concentrations in
settled dust to become airborne. There are no standards currently available
for assessing potential health consequences from asbestos through the
evaluation of wipe or microvacuum samples. A scientific peer review panel
(World Trade Center October 21- 22,2002 Peer Review Meeting Notes.
Available at www.tera.org.) recently evaluated the technical soundness of
estimating airborne asbestos concentration as a function of asbestos
concentration in settled dust for the purpose of setting health-based
benchmarks. The panel recommended against such an approach based on
the significant uncertainty associated with the numerous factors (such as
activity patterns, sample location, surface characteristics, air exchange rates
and room volume) that influence this relationship. EPA’s use of surface
wipe and microvacuum sampling at its WTC Residential Confirmation
Cleaning Study site (110 Liberty St.) was intended to provide a measure of
cleaning effectiveness, and not a risk-based health assessment. EPA’s
WTC Residential Confirmation Cleaning Study can be obtained at
http://www.epa.gov/wtc.
Primarily, risk from asbestos is directly related to its concentration in air.
Consequently, post-cleaning aggressive (i.e., use of a leaf blower and fans)
air sampling was conducted at 114 Liberty St. by DEP’s contractors to
insure that asbestos levels in air met regulatory-based and risk-based
clearance criteria.
The EMSL analytical report does not provide detailed information on
sample collection; however, it appears many samples were collected from
inaccessible areas below the hardwood flooring, or from areas of unknown
accessibility such as, wall tracking, pipe shafts and I-beams. The scope of
work developed for the clean up activities was designed for the removal of
debris from the collapse of the World Trade Center and did not include the
removal or remediation of pre-existing building materials. As a matter of
precaution, any residual dust and, thus, potential reservoirs of asbestos,
from currently accessible areas should be cleaned using the technique of
vacuuming and wet-wiping.
Asbestos containing materials (ACMs), such as floor tiles, were observed
during DEP’s cleaning of the building. Some of the ACMs may be present
under the hardwood flooring, thus samples collected from this location may
be more representative of the building materials contained within the
building rather than indicating contaminatios-from other sources.
Additionally, DEP noted and reported the presence of thermal system
insulation and damaged asbestos-containing fireproofing within the
building. Building representatives were provided with this information and
were informed of the provisions of Title 15, Chapter 1 of the Rules of the