submitted to the DEP. The unit should be set up so as to avoid tracking of
materials into already cleaned areas.
8. Isolation barriers shall be installed between unaffected areas and areas to be
cleaned.
9. A third party, who is independent of the asbestos abatement contractor, must
perform air sampling and analysis. Any person(s) who conducts sampling must
possess a valid NYS Asbestos Project Air Sampling Technician Certificate. Air
sampling must be performed in accordance with the requirements set forth in
Title 15, Chapter 1 of the Rules of the City of New York.
10. An “Asbestos Inspection Report” form, ACP 7, shall be submitted directly to
the DEP within one-week. The ACP 7 must list the emergency clean up
quantities in item 30.
11. Please note, the disturbance/ removal of in place material in the work place
is not permitted during clean-up activities unless the Department specifically
determines the need to abate damaged in place as part of the clean up. The
emergency phase of the project must be completed prior to in place ACM
abatement.
If you have any questions or require clarification, please do not hesitate to call
the Department at (718) DEP-HELP (24 hrs/7days).