submitted to the DEP. The unit should be set up so as to avoid tracking of into alw^dy
cleaned areas.
8. Isolation barriers shall be installed between unaffected areas and areas to be cleaned.
9. A third party, who is independent of the asbestos abatement contractor, must perform dr sampling
and analysis.. Any peraon(s) idio conducts sampling must possess a valid NYS Asbestos Project Air
Sampling technician Certificate. Air sampling must be performed in accordance with the
requirements set forth in Title 15, Chapter 1 of the Rules of the City of New York.
10. An “Asbestos Inspection Report” form, ACP 7, shall be submitted directly to the DEP within one-
week. The ACP 7 must list the emergency clean up qi^tities in item 30.
11. Please note, the disturbance/ removal of in place material in the work place is not permitted during
clean-up activities unless the Department specifically determines the need to abate damaged in place
as part of the clean up. The emergency phase of the project must be completed prior to in place ACM
abatement
If you have any questions or require clarification, please do not hesitate to call the Department at (718)f
DEP-HELP(24hrs/7days).