NYC 9/11 Public Portal Document
EPA / DEP meetirufwith Indoor Contractors
October 17,2002
Common Issues
Poor response to telephone calls.
One consultant mailed letters and access agreement to all the tenants/ occupants
requested apt cleanings. Another consultant emailed the same information.
Cancellation of the clean up by the tenants/ occupants on the scheduled cleaning day.
Consultants and contractors want some kind of compensation (4hrs / half a shift).
Security Clearance
The requirements are not clear. It can cost as much as $350 per person JE—
HVAC
Consultant Issues
Data entry and other administrative work takes a long time. One person is dedicated— *
to make all the (multiple) phone calls. X
Requested compensation '
Impossible to schedule more than 6-10 apartments / day
Project completion form is not ready (EPA)
Peeling paint
HVAC contractor is charging a lot of money
Can the analytical lab supply cassettes?
HVAC/Sttbbles
Contractor Issues
Waste manifest
One consultant is not letting the contractor work more than 6-7hrs a day& more than
15 apts. / day (Cole & JBH). Two year contract...
Work flow is not steady. Contractors need consistent amount of work. Unless this
problem is corrected we may have serious problems.
Apartment sizes are too big. Some of the terraces / balconies are huge- DEP
NYC-WTC_000151241
OCR can misread numbers and units. Confirm readings against the page image before using them.