Contractor issues memo, indoor air dust cleaning, Oct 2002

Machine-extracted title · confidence 90%

Memo summarizing contractor issues regarding the indoor air dust cleaning program in Lower Manhattan.

NYC-WTC_000130626–000130627

Folder label: “Indoor - Contractor Issues

Page image
Scanned page image, NYC-WTC_000130626
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

OCT-16-2002 17:56 EPA 212 637 3256 P.01i02

NYCDEP Meeting Agenda-October 17, 2002

Provided below is a list of issues raised by contractors hired by NYCDEP to complete the indoor air dust cleaning program in Lower Manhattan. The issues have been summarized and are as follows:

General Issues:

1) Conflicts between City contractors. How and who resolves them?

Monitoring Contractor Issues:

1) Mold and lead paint issue, is the process for evaluating established?

2) Chain of custody issues

3) Forms 2 Lite issues

4) Payment for dropping samples at lab?

5) Exhaust evaluations - need city to tell contractors payment will be a 5:1 ratio with hvac evaluations, need to know they have to be included in whole building evaluations, need to understand that evaluators have some discretion in how many get done

6) Payment for overseeing hvac evaluator?

Cleaning Contractor Issues:

1) Insurance-The City required cleaning contractors to have certain insurances in place before starting work. The contractor met this requirement. However, due to unexpected delays, work has not begun while the contactor continues to pay for this insurance coverage. The contractor has requested advance payment for the insurance cost as well as supplies and equipment purchased for this contract.

2) Carpets-The original bid package provided to contractors did not include a line item cost for the removal and disposal of carpeting. This needs to be incorporated into the contract if this service is being completed.

3) HVAC-All contractors need to have instruction on how the evaluation process works (direction from the City on how to charge inspections), how the cleanup of HVAC are awarded.

4) Cancellation charges-4.0 hours for cleaning contractor and 1 hour for monitoring. Is this right?

NYC-WTC 000130626

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000130626Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →