This contract between DEP and the monitoring contractor shall be in force for 24 consecutive months from
the commencement date. The monitoring contractormust be prepared to mobilize within 72 hours ofthe
contract award. Cleaning activities shall be scheduled for 20 residences per day. Air sampling shall be
scheduled and completed within 24 hours ofsuccessful visual inspection by the project monitor. Air
sampling shall also be provided at an additional 10 to 20 residences per day where cleaning activities are
not scheduled, (i.e. where residents have requested sampling only). Work shall be scheduled 7 days per
week between the hoursof8amand6pm.Asufficientnumberofproperlytrainedand certified personnel
shall be available for project monitoring and sampling.
The Monitoring Contractor shall have available sufficient quantities ofsampling equipment to provide the
amount and type ofsamples required for this proj ect At a minimum the following equipment is required:
air-sampling pumps with maximum flow rate capacities of 15 liters per minute, tripods, rotometers, sample
cassettes with mixed cellulose ester filters having pore size of 0.8um.
The Monitoring Contractor shall attend a kick offmeeting prior to commencement ofsampling activities.
At this time, the Monitoring Contractor shall participate in discussions regarding the scope of work,
sampling logistics and resource requirements and procedures for data acquisition and submital. In addition,
the monitoring contractor will demonstrate data acquisition procedures tod software to be employed for
this proj ect. The Monitor Contractor shall attend meetings or conference calk with EPA to coordinate field
activities, as requested.
The Monitoring Contractor shall adopt and follow the Quality Assurance Project Plan prepared by EPA
for all environmental data collection activities performed under this contact All appropriate data, original
field forms/data sheets, and chain-of-custody forms shall be collected and completed in accordance with
the instructions contained in the contract and provided to EPA. This information shall be provided via
FormsII Lite (F2L) or an alternative electronic format that is accessible by the laboratory. All clearance
air samples and copies ofnecessary documentation shall be hand delivered daily to EMSL Laboratories
at: 307 W. 38* St, New York, New York 212-290-0051. All wipe samples and copies of necessary
documentation shall be shipped daily by courier for next day delivery to Paradigm Analytical Laboratories
at: 2627 Northchase Parkway SE, Wilmington NC 28405,910-350-2839.
Copies of all invoices for work conducted under this contract shall be provided to EPA and DEP.
Decisions regarding the reimbursement of costs will be made by DEP.
Deliverables
All deliverables shall be provided via F2L or an agreed upon alternative electronic format approved by
EPA and DEP. The Project Monitor shall also maintain a copy of each deliverable and all field
documentation submitted under this contract for 365 days. The Project Monitor shall review all
deliverables prior to submission to EPA. The review shall assure that each deliverable is accurate and
complete, technically sound, and free of clerical errors