Indoor Air Residential Assistance Program
Monitoring Contract Scope of Work
DRAFT - 6/24/02
A. Introduction
All work performed under this contract must be in compliance with all applicable, relevant, and
appropriate regulations and this Scope of Work, including but not limited to those of the United States
Environmental Protection Agency (EPA), the United States, Department of Labor, Occupational Safety
and Health Administration (OSHA), the New York State Department of Labor (NYSDOL), theNew
York State Department of Health Environmental Laboratory Approval Program (ELAP) and the New
York City Department of Environmental Protection (NYGDEP). This project shall involve site
inspections, surveys, and assessments, scheduling, coordinating and monitoring the clean up of
dust/debris and sampling from building apartments impacted by the collapse of the World Trade
Center.
B. Roles and Responsibilities - ‘
The USEPA has overall responsibility for insuring that work conducted as part of the Indoor Air
Residential Assistance Program is completed safely, efficiently and in a compliance with the Scope of
Work. As such, EPA shall have the following authorities relating to work conducted under this
contract:
1. The authority to stop work for health and safety reasons or for non-compliance with the Scope
ofWoik.
2. The authority to direct the contractor in the performance of the work.
3. The authority to review and approve or disapprove of the qualifications of all contractor
personnel involved in the work.
4. The right to receive, inspect and accept or reject any work.
C, Qualifications
Proof of qualifications must be presented upon request, including qualifications for wipe sampling,
personal monitoring and HVAC evaluations.
Project Monitors
The Project Monitors must possess valid NYS Asbestos Project Monitor certificates. Project Monitors
must have served as a third party project monitor on at least 20 asbestos abatement projects. Project
Monitor must have performed final clearance inspections on at least 50 asbestos abatement projects.
The Project Monitor must have access to translation services to schedule pre cleaning unit inspections