Nextel phones and Service 10 phones at $65/month
for 18 months $ 11,700
Car rental-GSA 3 Vehicles - Mid size wagon or equivalent
$236/month x 3 vehicles for 18 months $ 12,800
Rental of Parking Spaces $ 35,000
Personal Protective Equipment
27,216 changeouts x $ 15 (booties and cartridges) $ 408,240
Air Monitoring Equipment, Purchase & Rental $ 30,000
Total Equipment & Supply Cost $ 52X024
Total L4G Costs $ 19,547,984
Includes costs of EPA’s salary and travel, contractor services and equipment
and supplies.
Overhead Costs
Based on previously negotiated rates.
7. Funding
FEMA agrees to fund the project at a cost not to exceed $ 19,547,984.
8. Period of Performance
The period of performance for this Interagency Agreement shall begin on the date both Agencies agree
to this lAG and conclude on January 30,2004.
* Pursuant to 44 CFR § 206.8, regular labor for permanent Federal agency personnel (e.g. personnel
whose Federal agency has received an appropriation from Congress or employees who backfill for
employees working on the project that is the subject of this Agreement), and overhead costs are not
eligible for reimbursement, except when the costs incurred would normally be paid from a trust,
revolving, or other fund. For the latter exception, EPA’s Financial Manager must submit a written
certification that the overhead costs and costs for regular labor are paid from a trust, revolving, or other
fund. If regular time is allowed, it should be identified separately from overtime labor on the invoice by
description.
** When FEMA pays for the purchase of equipment under an Interagency Agreement or Mission
Assignment, the equipment normally belongs to FEMA and must be fully accounted for after the project
is completed.