Distribution of updated statement of work documents for WTC cleaning and monitoring programs.

NYC-WTC_000138585–000138604

Folder label: “E-Mails Hotline M. Gilsenan

Page image
Scanned page image, NYC-WTC_000138601
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Deliverables

The Project Monitor shall review all deliverables prior to submission to EPA. The review shall assure that each deliverable is accurate and complete, technically sound, and ftee ofclerical errors.

The Project Monitor shall submit upon request afield package consisting offield sheets, field notes (copy), and chain-of-custody forms (copy) shall be delivered to the EPA via email, or an alternative format agreed upon. The Contractormust sign and date all field sheets, fieldlogbooks and chain- of-custody forms. This data shall be provided daily upon request at^e activity completion.

12. The Proj ect Monitor shall perform final visual inspections upon completion ofthe cleaning. Ifall areas are not dust free then the Project Monitor will dSrect the Cleaning Contractor to reclean as necessaiy. Ifall areas are dust free then the Proj ect Monitor will authorize final air sampling. Final inspections shall be documented using the Cleaning Checklist,

Deliverables

The Proj ect Monitor shall review all deliverables prior to submission to EPA. The review shall assure that each deliverable is accurate and complete, technically sound, and free ofclerical errors.

The Project Monitor shall submit uponrequest to EPA copiesofthe log bookpages via email, fax, or alternative format agreed upon.

13. The Project Monitor willl^bduct a post-cleaning inspection ofthe apartment with the resident at the completion ofthe sampling. The resident should inspect the apartment and identify any damage at this time and sign-offon the Project Completion Form. Any damage or loss to an apartment or its contents shall be documented on this form.

Deliverables

The Project Monitor sb® review all deliverables prior to submission to EPA. The review shall assure that each deliverable is accurate and complete, technically sound, and free ofclerical errors.

The Project Monitor shall submit upon request to the EPA copies ofthe log book as requested via fax or alternative format agreed upon and within two days ofrequest. Final air sampling shall be performed with 24 hours of final visual inspection.

14. Post Clean-up Air Sampling Procedures a. Sampling shall not begin until a visual inspection confirms the absence ofvisible dust and debris. Post cleaning air sampling shall be performed upon successful visual inspection and completed within 24 hours. A successful visual inspection shall be an inspection that verifies the absence of dust and debris.

NYC-WTC_000138601

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000138601Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →