condition. They have prepared a blind flange for permanent installation and have done necessary
preparation work to remove the valve, including removal of the gear mechanism. The intention is
to remove the valve stem, the bonnet, and then the body of the valve itself. They will be using a
hoisting system devised by our machinists. The work is scheduled to begin on Saturday February
17, 2001 due to distribution concerns.
Springfield Gardens Industrial Park (Air Freight Area) (a/k/a SE-727); Queens
Springfield Gardens Residential Areas (a/k/a SE-727A and SE-727B); Queens
The next meeting of the Springfield Gardens Task Force team consisting of DEP, Department of
Design and Construction (DDC) and the Economic Development Corporation (EDC) took place on
Thursday, February 15, 2001. Currently, the Task Force anticipates meeting its goals for the next
series of action dates for the project. The targeted bid date for the project is March 1, 2001. The next
progress report to the Borough President has been moved up to Friday, March 16, 2001. At the last
meeting, additional comments from the NYS Department of Environmental Conservation (DEC)
were received which were forwarded to DEP's OEPA Office for review with DEC. It is hoped that
the State DEC permit will be secured prior to the project bid date.
Local Law 65/96 Notifications and Notices of Violations (NOV); Citywide
Three (3) homeowners in the Broad Channel area of Queens, who failed to respond to several prior
LL 65196 notices to connect to the public sewer, failed to appear at an Environmental Control Board
(ECB) after being subject to a board Cease and Desist Order. As a result, the Board ordered the
homeowner's water be shut off. However, after receiving the shut off notices, the three homeowners
each contacted ECB and arranged for hearings, thereby postponing the shutoff of their water service
pending the outcome of the hearings.
Septic Failure at 227 Kramer Avenue; Staten Island
At the request of the NYC Department of Health, inspectors from DEP posted a Water Shutoff
Notice at 227 Kramer Avenue due to an overflowing septic system condition. The Shutoff Order was
scheduled for February 7, 2001; but was postponed at the request of NYC DOH. The homeowner
finally took corrective measures and had their septic system pumped out and treated with chemical
cleaner. DEP will continue to monitor the situation on a daily basis until the overflow situation is
fully addressed.
c: Deputy Mayor Joseph J. Lhota
Deputy Mayor Robert M. Harding
Deputy Mayor Anthony P. Coles
Deputy Mayor Rudy Washington