Part III — Health & Safety Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701— Rev 3, August 29, 2005
incident to the Building. The SSO will provide the "all clear" signal to the contractor site
managers once it is safe to return to normal work operations.
2.16 Response to Specific Emergency Events
Below is a list of unplanned events that may occur during the deconstruction project. This list
may not be all encompassing, but represents "events" related to similar projects. These events
include:
• Fire or explosion
• Power failure
• Structural failure
• Worker injury or illness
2.16.1 Fire or Explosion
In the event of an explosion or a fire, the SSO shall immediately:
1. Call 911
2. Initiate building evacuation procedures as outlined in Section 2.15 of this
HASP
3. Meet First responders at the pre-designated location (unless circumstances
dictate otherwise, it is the security desk at the Building) for briefing on the
scope and nature of the emergency
4. Notify OWNER
Should there be a work stoppage in a certain area due to a fire or an explosion, work will not
resume until the SSO verifies that appropriate corrective actions have been taken.
2.16.2 Power Failure
In the event of a power failure, the SSO shall immediately:
1. Call 911, if warranted
2. Coordinate with the site manager and abatement contractor to initiate
containment isolation activities (e.g. both the Personnel and Waste Load Out
Decontamination units must be immediately sealed to prevent a fiber release).
3. All containment isolation barriers are to remain secure until the required
negative pressure has been re-established.
2.16.3 Structural Failure
Deconstruction process will create weakened sections as supporting elements are removed, such
as roof sheathing, wall sheathing. In the event of a unanticipated structural failure, the SSO shall
immediately:
1. Call 911, if warranted
37