Health and safety plan Part II, 30 Warren Street, January

Machine-extracted title · confidence 100%

Part II of a health and safety plan for remediation and deconstruction at 30 Warren Street in January 2006.

NYC-WTC_000096623–000096675

Folder label: “201 WARREN STREET Block: 16 Lot: 220

Page image
Scanned page image, NYC-WTC_000096666
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Regulatory Submittal Part III — Health & Safety Plan Fiterman Hall — 30 West Broadway, New York, New York Airtek Project 05-0867 — January 10, 2006

Should there be a work stoppage in a certain area due to a fire or an explosion, work will not resume until the CSO verifies that appropriate corrective actions have been taken.

16.2 POWER FAILURE

In the event of a power failure, the CSO shall immediately:

1. Call 911, if warranted; 2. Notify on site Electrician to evaluate issue; 3. Coordinate with the Site Manager to initiate containment isolation activities to include; 4. Immediately seal Personnel and Waste Load Out Decontamination units to prevent a fiber release until power is restored; 5. Coordinate with the Site Manager to initiate back-up power generation; and 6. All containment isolation barriers are to remain secure until the required negative pressure has been re-established.

16.3 STRUCTURAL FAILURE

Deconstruction process will create weakened sections as supporting elements are removed, such as roof sheathing, wall sheathing. In the event of an unanticipated structural failure, the CSO shall immediately:

1. Call 911, if warranted; 2. Coordinate with the site manager and abatement contractor to initiate containment isolation activities (e.g. both the Personnel and Waste Load Out Decontamination units must be immediately sealed to prevent a fiber release); and 3. All containment isolation barriers are to remain secure until the required negative pressure has been re-established.

16.4 MEDICAL EMERGENCY

The first worker who notices that a medical emergency or personal injury has occurred shall immediately make a subjective decision as to whether the emergency is life threatening and/or otherwise serious.

Potential injuries that may result in a medical emergency include:

• Slips, trips, falls, lacerations • Trauma injuries caused by being struck by heavy equipment, building components, waste containers, etc. • Eye injuries • Burns from electrical, fire or explosion • Electrical contact or electrocution • Heat stress/stroke • Chemical exposures • Cardiac emergencies • Respiratory emergencies

The Contractor and its subcontractors will respond to minor injuries requiring first aid only; major injuries or requirements for search and rescue will be handled by First Responders.

44

NYC-WTC 000096666

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000096666Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000165900 · Box 7DDC

Document page containing contact details for Con Edison and JWC Environmental Health & Safety personnel.

Cited alongside this record in an Ask answer

Compare copies and versions →