Part III — Health & Safety Plan
133-135 Greenwich StreetI21-23 Thames Street
Airtek Project 05-0701— Rev 3, August 29, 2005
Section 2.8 provides information concerning the management of hazardous chemicals on-site and
the site Hazard Communication Program.
2.2.5 Biological Hazards
Biological concerns in the work area are primarily, insects, rodents, and mold/fungi.
2.2.5.1 Insects
The presence of insects shall be addressed by personnel as the insects are encountered. When a
stinging or poisonous insect, such as a bee or spider, is identified, personnel should exercise
caution to avoid being bitten or stung for example by using tools to move material. In the event
that a person is stung or bitten, the incident shall be reported to the Site Manager for the
Subcontractor who shall report the incident to the CSO. The Site Manager for the Subcontractor
shall initiate actions to manage and address the bite or sting. Personnel who are allergic to insect
bites and stings should identify their allergy to their employer.
2.2.5.2 Rodents
In the event that rodents or animal pests are identified or observed on-site, the Subcontractor
Manager should report the incident to the Contractor CSO. The Contractor shall be responsible
for evaluating the condition and implementing steps to eliminate rodents on the site.
2.2.5.3 Mold/Fungi
The initial building walk-though by Airtek environmental identified mold contaminated building
materials/components within the Building. The identification of additional mold/fungi on-site
will be made based on visual inspections of building materials. When mold/fungi are identified,
the removal of impacted materials shall be addressed concurrently with Asbestos Abatement
Activities. Removal and handling measures shall be consistent with the NYC Department of
Health and Mental Hygiene "Guidelines on Assessment and Remediation of Fungi in Indoor
Environments."
2.3 ENGINEERING CONTROLS
Engineering controls will be used as primary protective mechanisms to protect the safety and
health of all employees whenever technically feasible, and prior to the implementation of
Administrative Controls and/or personal protective equipment. Each Subcontractor shall be
responsible for the provision and implementation of the following:
• Construction/demolition dust suppression materials and equipment to include:
o HEPA-filtered air filtration devices to reduce area dust levels.
o Vacuum cleaners equipped with HEPA filters.