NYC 9/11 Public Portal Document
5. Electrical Wire Insulation
6. Roofing Products
7. Brick Mortar
• 8. Window Caulk & Glazing
Based on the currently recommended sampling and analytical procedures, Airtek recommends
that additional sampling is necessary, in order to determine the asbestos content of building
materials.
3.0 SUMMARY OF AIRTEK ENVIRONMENTAL'S INSPECTION RESULTS:
The asbestos inspection was conducted on 5/26/05 & 5/27/05 and involved a thorough visual
examination of all areas and sampling of suspect materials that would be impacted during the
proposed demolition.
Airtek Laboratory analysis confirmed the presence of asbestos in the amount greater than 1%
within the samples collected from the following material:
1. Bulkhead Tar
Airtek laboratory analysis determined the samples collected from the following materials to
contain less then one percent (<1%) asbestos.
1. Textured Ceiling
2. Carpet Mastic
3. Ceiling Tiles
4. Floor Tile Grout
5. Tar on HVAC Ducts
. 6. Wall Tile Grout
7. Wall Tile Glue
8. 12" x 12" Floor Tiles & Mastic
9. Electric Wire Insulation
10. Sheetrock & Joint Compound
4.0 CONCLUSIONS AND RECOMMENDATIONS:
Asbestos-containing materials, which will be affected by the scope of work, have been positively
identified at various locations throughout the building(s).
Proper asbestos abatement procedures shall be implemented prior to the commencement of
demolition work. All asbestos abatement work shall be performed in accordance with all
applicable Federal, State and Local rules and regulations. The abatement project shall be filed
with all agencies having jurisdiction over this project, such as USEPA, NYSDOL and NYCDEP.
A licensed abatement contractor must perform the removal of all friable and non-friable ACM.
Airtek believes that the implementation of these recommendations will serve to best protect
human health and the environment.
To assure that the removal of the aforementioned ACM is properly and effectively carried out,
the following recommendations are proposed by Airtek:
A. Develop and implement a schedule that outlines the time frame for removal of ACM.
B. Develop complete and concise specifications to effectively deal with removal of the ACM.
These specifications should be developed to comply with all applicable Federal, State and
• Local regulations.
C. Retain the service of an independent testing laboratory to monitor the air for possible
asbestos contamination before, during and after the removal work. Retain all
documentation and correspondence from the removal contractor, the testing laboratory and
related items in a permanent record.