Asbestos abatement technical specifications, 130 Cedar Street, July 2004

Machine-extracted title · confidence 100%

Technical specifications document prepared for asbestos abatement work at the 130 Cedar Street site.

NYC-WTC_000125579–000125652

Folder label: “130 CEDAR STREET

Page image
Scanned page image, NYC-WTC_000125583
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Asbestos Abatement Technical Specifications For 130 Cedar Street, New York, NY

SECTION ONE: SCOPE OF WORK

1.0 Description of the Work

1.1 The work specified herein shall be the removal, as indicated, of ACM from the locations of the subject property by competent persons who are trained, knowledgeable, qualified and licensed in the techniques of abatement, handling and disposal of asbestos-containing and asbestos-contaminated materials and the subsequent cleaning of contaminated areas.

1.2 The asbestos abatement contractor (the Contractor) shall supply all labor, material services, insurance, permits and equipment necessary to carry out the work.

2.0 Work Summary

2.1 Bids shall be submitted for the implementation of the scope of work for asbestos removal at 130 Cedar Street, as outlined in Section 10 "Asbestos Quantity Schedules".

3.0 Sequence of Work

3.1 The Contractor shall adhere to the following sequence of tasks:

a. Construction of decontamination systems as required •

b. Sealing of all vents, drains, fan units, motors, belt housings, light switch fixtures, etc. with critical barriers composed of two (2) layers of 6-mil fire retardant polyethylene sheeting

c. Work area preparation: All surfaces in the work area shall be covered with two (2) layers of 6-mil fire retardant polyethylene sheeting to create an airtight enclosure. Negative air filtration systems shall be installed with sufficient negative pressure to maintain a minimum of four (4) air changes per hour.

d. Work area preparation for asbestos abatement as required.

e. Removal of all ACM from proposed _work areas and Occupational Health and Safety Administration (OSHA) personal monitoring during this removal.

f. Clean up, final clean-up and load out of all ACM.

g. Transportation of ACM to an approved landfill.

h. Final clean up and removal of equipment and materials after clearance has been attained. •

Prepared by JLC Environmental Consultants, Inc. Project No. 04-3271 Page 5

NYC-WTC 000125583

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000125583Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000127738 · Box DEP Box 52

Health and safety plan for Phase I deconstruction at 133-135 Greenwich Street and 21-23 Thames Street dated June 8, 2005.

Cited alongside this record in an Ask answer

Compare copies and versions →