Asbestos abatement technical specifications, 130 Cedar Street, July 2004

Machine-extracted title · confidence 100%

Technical specifications document prepared for asbestos abatement work at the 130 Cedar Street site.

NYC-WTC_000125579–000125652

Folder label: “130 CEDAR STREET

Page image
Scanned page image, NYC-WTC_000125597
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Asbestos Abatement Technical Specifications For 130 Cedar Street, New York, NY 5.2 The superintendent or supervisor shall maintain a permanently bound project logbook that will:

a. Identify the facility, Owner(s), Agent, Contractors and project.

b. Define each work area.

c. Record completely all pertinent facts relating to the project.

d. Record date, time and name after each entry.

e. Have a daily sign-in for each and every individual entering into the work area. They must provide, In legible print, name (first and last), worker license number, the time and date entered and exited and proof of approved visitor status.

f. Dates of Inspections and documentation of pass/fall of inspections.

g. A summary of work accomplished at the end of each shift.

h. Notes and comments.

5.3. The project supervisor shall also be responsible for the following tasks:

a. Assuring that the decontamination chambers are kept clean.

b. Surveying the work area a minimum of two (2) times per shift for proper housekeeping, safety precautions, barrier integrity and integrity of any air hoses. He shall record objective observations.

c. Ensure that each worker is wearing proper personal protective equipment and is trained in Its use, and shall Instruct workers on evacuation procedures during air compressor breakdown.

d. Ensure that all workers are certified and licensed.

e. Take precautions to prevent over stressing workers.

f. Ensure worker qualifications consist of the following:

1) Training, as evidenced by the participation in, successful completion of, and certification by a NYC-DEP and NYS-DOL approved asbestos handler's course.

2) Familiarization with the standard operating procedures for asbestos abatement work.

3) Skills and experience with all phases of abatement work as evidenced by participation In at least two asbestos abatement projects similar in size and scope.

Prepared by JLC Environmental Consultants, Inc. Project No. 04-3271 Page 19

NYC-WTC 000125597

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000125597Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000127738 · Box DEP Box 52

Health and safety plan for Phase I deconstruction at 133-135 Greenwich Street and 21-23 Thames Street dated June 8, 2005.

Cited alongside this record in an Ask answer

Compare copies and versions →