130 Cedar Street July 15, 2004
Selective Demoltion and Façade Restoration Koenen Associates
D. The guarantees shall cover any and all work done under this contract, either by
the Contract Subcontractors. All guarantees shall bear the endorsement of
Contractor in writing.
E. The correction of such work shall include without additional charge, all additional
expenses, and damages In connection with such removal, replacement of any, or
part, of the work which may be damaged or distributed thereby.
F. Form of Guarantee: The Contractor shall use the form found at the end of this
Section for presentation of their guarantees.
1.09 KEYS AND MAINTENANCE KITS
A. All keys, maintenance kits or stock, replacement parts of materials, spare
construction material, and equipment required under the contract shall be stored
in the completed building in specific areas as designated by the Owner.
1.10 PROJECT CLOSE-OUT DOCUMENTATION
A. Prior to final payment, the Contractor shall submit to the Architect the following
documents in an original and one copy unless otherwise noted:
1. A complete listing of all trade Subcontractors, business addresses and
items supplied by such trade Subcontractor.
2. A listing of manufacturers of major materials, equipment and systems
Installed In the work.
3. Payment of Debts and Claims and Consent of Surely: Adequate
evidence that he has paid all obligations arising out of the Construction
Contract. He shall submit AIA Document No. G-706, contractor's •
Affidavit of Payment of Debts and Claims, together with AIA Document
G-707, Consent of Surety, Indicating written consent of the surety to final
payment.
4. Release of Uens: Each Contractor shall also submit AIA Document G-
706-A, contractor's Affidavit of Release Uens, indicating that the release
for waivers submitted are exceptions that they be so stated specifically in
this form. Contractor and all Subcontractors and suppliers shall in
addition submit any other release documentation required by the Owner.
5. Test Data: A copy of all test data taken.
6. All warranties, guarantees, maintenance agreements and similar
provisions of the contract documents.
7. Final progress photographs.
8. A complete punch list signed off by General Contractor as being
completed.
9. Operating and maintenance Instructions, keys, and maintenance kits.
10. Project record documents as described herein.
1.11 CERTIFICATE OF OCCUPANCY
•
Contract Close-Out 01700-4
NYC-WTC 000125148