SECTION 01500
CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS •
PART 1.00 - GENERAL
1.01 GENERAL REQUIREMENTS
A. Work of this Section, as shown or specified, shall be in accordance with the requirements
of the Contract Documents.
1.02 WORK INCLUDED
A. Work of this Section Includes all labor, materials, equipment, and services necessary to
complete the construction facilities and temporary controls as shown on the drawings and
specified herein, Including but not limited to, the following:
1. Hoists, stairs, and ladders.
2. Rodent control.
3. Field office.
4. Fire protection.
5. Temporary utilities.
6. Temporary toilets.
•:
7. Temporary site access.
8. Security.
9. Snow control
10. Environmental controls.
11. Elevator.
1.03 RELATED WORK
A. Cleaning - Section 01505.
B. Materials and equipment - Section 01600.
PART 2.00 - PRODUCTS
2.01 GENERAL
A. Arrange for and provide temporary facilities and controls as specified herein and as
required for the proper and expeditious prosecution of the work. Pay all costs, except as
•
Construction Facilities and Temporary Controls 01500-1
NYC-WTC 000125130