studies, immediately after the incident and since. We followed the advice of
our Environmental Consultants and mobilized cleanup operations. In addition,
my peers from Mount Sinai NYU Health really came to our rescue. After
working around the clock for over 80 hours, I could see my staff needed rest.
All of the pre and bag filters on 25 or so air handling units had to be
changed before the Engineering Department could restore the building to
normal operations. A team of 25 HVAC Mechanics and Electricians from Mount
Sinai and NYU Medical Center came to our rescue on Saturday morning. They
worked like gangbusters performing preventative maintenance on each of the
units, washing heating and cooling coils, replacing all HVAC filters,
greasing bearings and motors, and replacing belts. They also relieved my
staff by provided electricians to continually monitor the emergency
generator. I am grateful and indebted for their assistance during the
Crisis, since without their assistance, it would have taken weeks to prepare
the Hospital's physical plant back for normal operations.
I must say that every single Engineering Department employee at NYU Downtown
Hospital did an outstanding job of responding to the many needs of the
facility. They demonstrated extraordinary courage and dedication to the
Hospital, its patients, and Community we serve.
Being informed by Con Edison that the power interruption was likely and would
probably last another week, we were concerned that our emergency generator
had been running for (4) days,. With the assistance of Mount Sinai NYU Health
and HO Penn, we secured a larger generator (1875kW). We requested that Con
Edison remove the smaller generator and disconnect us from their electrical
grid. Late Saturday evening, the larger generator on the street was
connected to the normal distribution service and power was systematically
transferred from our emergency generator on the roof to the temporary one on
the street. After the generator on the street was fully loaded, our
emergency generator went into it's cool-down cycle and stopped, after running
for over 110 hours. HO Penn performed a quick PM on our generator, while the
Hospital's normal power was now being fed by the temporary generator on the
street, a much more stable environment. Monday morning, 140 hours after the
incident, Con Edison finally tied the Hospital back onto a temporary
electrical grid.
As of today, Tuesday, September 25, 2001, the Hospital continues to be very
seriously affected by the tragedy. Access to the facility is blocked by
police barricades and National Guard, so it is very difficult for staff and
patients to travel to the hospital. Patients who come by car are turned
away. Even some staff --- when deemed "non-essentials" by the police at the
roadblocks --- are turned away. Wires from Con Edison's temporary power grid
are still running along every sidewalk, and phone service is still out to our
Faculty Practice and off-site offices.