May 13, 2003
Ms. Penny Theodorellys
New York City Department of Environmental Protection
59-17 Junction Boulevard, 11th Floor
Corona, NY 11368
Reference: Asbestos Project Monitoring/Air Monitoring and HAZMAT
Consultant for 114 Liberty St-Contract# WTC-LBA
Request for a Change Order, Additional Work Schedule
Dear Ms. Theoderellys:
JLC Environmental Consultants, Inc. (JLC) appreciates your continued
consideration for the provision of specialized Asbestos and HAZMAT Services.
We would like you to process a request for payment for additional work. Our
original bid covered the work for a period not to exceed three weeks (see
attached addendum #2). This consideration entitled the monitoring of the
removal in that time period. However, the removal has taken longer.
Additional hours and resources were spent; as a result there was a duplication of
work. If the work had taken place in the allotted time period no additional man
hours and air monitoring tests would have been required, since the work would
have been part of the over-all project. However, the second mobilization
required the duplication of work in terms or man-hours and air monitoring tests.
These additional resources were not part of our original Lump Sum quotation.
I would like to present for your examination the following break down for the
additional mobilization:
DATE Proj. Mang. Proj. Mont. Air Tech. PCM TEM
3/26-4/6 9 hrs. 163.5 hrs. 95 hrs. -50 50
I have forwarded the time sheets, daily logs and air monitoring results as back-up
information for your examination. We would like to utilize for the provision of
additional services (Add-Alternate). We are requesting a change order based on
the above referenced facts for the following amount: