Contract specifications for decontamination, 110 Church Street, Oct 2001

Machine-extracted title · confidence 90%

Contract specifications outlining site decontamination and asbestos disposal procedures for 110 Church Street.

NYC-WTC_000098612–000098643

Folder label: “32 PARK PLACE Block: 126 Lot: 2 Soe 7 BIN: 1001410 110 Church Street, 50 Murray Street

Page image
Scanned page image, NYC-WTC_000098627
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

I 20. SAFETY DURING CONSTRUCTION:

a) The Contractor shall enforce suitable rules and provide the required guards and protective devices for the safe execution of the work and for the safety and health of the men employed on it and the public in general, both inside and outside the limits of the contract. The Occupational Safety and Health Act shall be strictly observed by the Contractor. Job site safety is the responsibility of the Contractor.

b) All prime Contractors and all Subcontractors shall immediately report all accidents such as injuries, or health hazards, in writing, to the Owner and Consultant, or their designated representatives.

21. AIR MONITORING:

All air monitoring tests required by the Contract Documents shall be furnished and paid for by the Owner. All costs for OSHA required monitoring shall be borne by the Contractor.

22. REMOVALS OF RUBBISH AND WASTE MATERIALS:

Continuously as the work progresses during the performance of the contract, the Contractor shall clean up and remove from the building and away from Owner's premises, all rubbish, debris, and waste materials resulting from their operations.

23. MOVING MATERIALS, EQUIPMENT, MECHANICAL, ELECTRICAL INSTALLATIONS, ETC.:

If it becomes necessary at any time during the execution of the work to move materials or equipment to facilitate the work, the Contractor shall move them or cause them to be moved and/or reinstalled without additional charge.

24. SCAFFOLDS, LADDERS, RUNS, AND HOISTS:

The Contractor shall construct and maintain such temporary scaffolds, ladders, runs, hoists, centering, shoring, and other facilities as required to construct the work under the contract.

25. TEMPORARY CLOSURES:

a) If directed by the Owner, the Contractor shall furnish and install weathertight temporary closure at all openings in exterior walls and roofs including door, louver and window openings during cold and inclement weather, as required for construction and interior finished installation, and for the maintenance of a specified inside temperature.

I SC-5

NYC-WTC 000098627

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000098627Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Buildings in this record

Machine-extracted building matches; verify each source. Buildings, never households.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →