'IL GROUP,INC.
PROGRESS REPORT
PARAMOUNT GROUP, INC 180 MAIDEN LANE
To: Mike Versace, N. Bellion
From: Paul Neira
Date: September 22, 2001
Subject: Clean up of fresh air intakes & plenums.
At approximately 6pm, I met with Robert from AI/AA and made a preliminary walkthrough of
the work area and work to be performed. We coordinated with security and after inspection of the vehicle
and equipment I issued temporary passes to the following individuals:
German Torre P11 _._._._._ Hector Vindel PII Jose Rendon PII
Gonzalo Arias-.- -.- P11 Rodolfo Sabillon Pig Miguel Palomeque _ _ _ _ _ _ P11
Juan Palomeque._._. !!LJ Ismael NunezL f1LJ Laila
Pablo Palomeque PII j Edgar Asmal PII
All equipment and personnel were then moved to the 5`1i floor and primary containment was setup between
fans 2 & 3. AA/AI Supervisor briefed workers as to the work to be performed, while engineering notified
tenants of HVAC shutdown. I spoke with the supervisor regarding concerns I had on protecting the fan
intakes, removal of the pigeon grating and the louver, slope cleaning process.
Engineering assisted AI/AA with power and water hook ups, provided pressure washer and instructed
personnel on procedures for filter removal. Secured freight elevator for transportation of dirty filters to loading
dock. Engineering also had to snake one of the drains in the plenum for water removal, for all other areas the
floors were vacuumed.