NYC 9/11 Public Portal Document
Environmental Site Characterization — Facade Report
Fiterman Hall — 30 West Broadway, New Yoric, NY
Airtek Project 05-0867 —January 10, 2006
4.0 PROJECT-RELATED CONCLUSIONS
4.1 WTC Dust Impact - Exterior Cleaning Requirements
Only the ground floor, portions of the second floor and the gash area must be
subject to focused cleaning by a certified abatement contractor. This will be
conducted by the Contractor as a part of the Remediation or Deconstruction
Phase of the project. This will allow the erection of the project exterior scaffold
to be delayed until the scaffold is needed for deconstruction work
4.2 Facade Integrity
With the exception of the gash area, the facade is intact. The facade system was
designed and built to be an impermeable barrier, and it has retained these
qualities. The window systems are in excellent condition and are a serviceable
barrier for use during the abatement. The installation of plywood/plastic critical
barriers over the windows is not necessary to carry out the remediation of the
Building. The operating awning-window panels can be sealed with caulk and
critical barriers for the remediation phase. This, too, will allow the erection of
the project exterior scaffold to be delayed until the scaffold is needed for
deconstruction work.
4.3 WTC Dust Impact — Facade Components
The exterior of the facade was effectively cleaned by the NYC DEP facade
cleaning program. Build-up of urban road dust on the ground 'floor and isolated
pockets of WTC debris will be subject to focused cleaning by the Contractor. The
gash area will be cleaned from the slabs themselves. The interior of the facade
will be cleaned during the Remediation Phase of the project.
4.4 Asbestos-Containing Building Materials
Asbestos-containing materials exist on and within the facade, but neither of these
ACBMs impact the facade's integrity as a contaminant barrier during the
Remediation Phase of the project. The interior vapor barrier will be abed during
the remediation phase of the project, and the non-friable lintel flashing will be
abated during the Deconstruction Phase of the project.
4.5 Lead-Based Paint Components
Facade components are not coated with lead-based paint.
NYC-WTC 000096509
OCR can misread numbers and units. Confirm readings against the page image before using them.