NYC 9/11 Public Portal Document
Regulatory Submittal Part I — Work Plan
Fiterman Hall — 30 West Broadway, New York, New York
Airtek Project 05-0867 — January t0, 2006
6.1 Operation I — Clean Zone Decontamination & Clearance
The first operation to be conducted will be the decontamination and
environmental clearance testing of three areas of the first floor of the Building. As
illustrated in Attachment III— Remediation Phasing Plan 1-A, these areas include
Clean Zones 1, 2 & 3. Clean Zone I is the northeast corner of the first floor,
where site offices for project management (DASNY/PCF Team/Contractor) will
be established. Clean Zone 2 will include the loading dock areas where
decontamination units will be located and transport loading will be conducted. At
the request of the Regulators, Clean Zone 3 will be created to house the regulated
waste storage areas so that these areas may be inspected by the Regulators
without requiring entry to contaminated spaces. These areas will be sealed-off
from the rest of the Building, gut-stripped and decontaminated, and then subjected
to clearance testing as detailed in Section 7.0 below. Daily monitoring for
asbestos will be conducted to verify the effectiveness of the engineering controls
established to prevent re-contamination of the Clean Zones.
6.2 Operation II — Exterior Cleaning
As detailed in the Facade Characterization Report, the exterior of the building
was decontaminated as a part of the NYC DEP Building Exterior Cleaning
Program following 9/11/01. Limited exterior cleaning is still required at specific
points noted during the characterization study, and on the lower two floors where
urban background road dust has built up on the facade components. Focused
exterior cleaning will be conducted by wet wiping and HEPA-vacuuming of the
impacted facade components, using methods intended to prevent fugitive cleaning
water. Exterior cleaning of the lower sections of the building will be conducted at
the start of the project, and areas requiring scaffolding for cleaning operations will
be cleaned as the scaffolding is erected. This work may overlap Operation III - the
interior gut strip discussed below.
63 Operation III - Gut Strip
6.3.1 Building Envelope Preparation Work
The Gut-Strip will be conducted in negative air full-containment as an
asbestos project according to the asbestos rules and NYC DOL Variance
for the project. As detailed in the Facade Characterization Report, the
facade of the building is in good condition. The interior surface of
operable windows within the ribbon window system of the building will
be HEPA vacuumed, wet wiped and sealed with two layers of 6-mil
polyethylene sheeting, spray-glue and duct tape (NYS DOL Critical
Barrier). The operable portions (frames, hinges, wells) of these windows
will be cleaned during the scaffold erection (Section 7.3), and the plastic
and duct tape will be removed at that time. In the "Gash Area" of the south
8
NYC-WTC 000095751