NYC 9/11 Public Portal Document
Mr. Chris Alonge - NYS DOL
Variance Re-Opening Request - File 05-0919
Airtek Project # 05-0867 - November 17, 2005
Temporary Safety and Elevator/Utility Restoration:
Electrical Service: Temporary power was provided to the building so that
CUNY and DDC and their contractors could activate one elevator, remove
debris, perform safety work, and restore minimal building power and emergency
lighting. An 800 amp, 208 volt, 3 phase, temporary electrical service was installed
and currently provides power to the building. This power has been determined
to be inadequate for the remediation and demolition work phases that will be
performed over the course of a year.
Four low rise, four high rise and one service elevator must be restored to service
in order to remove the large quantity of interior demolition/remediation debris
from the building during the remediation (abatement) phase. One prerequisite
to restoring elevator service is providing adequate power to run them.
Therefore, based on direction from Con Edison, a portion of the original electrical
service will be re-energized.
Approximately ten electricians will be on site. They will:
1. Inspect and energize all egress light fixtures serving major mechanical
spaces, stairwells and pathways and replace lamps as required.
2. Inspect, HEPA-Vacuum as necessary to "gross clean," and exercise (put
through numerous on/ off cycles) service and distribution switchboards
including re-torqueing all buss work in the switchboards. All cleaning
(HEPA-Vacuuming/ Wet-wiping) will be conducted by a NYS DOL
Certified Asbestos Contractor.
3. Megger all major feeders from both the service and distribution
switchboards.
4. Remove temporary feeders from Emergency Service Switchboards and
extend and reconnect the temporary service to the main of each Service
Switchboard.
5. Restore power to local Power and Lighting Panels and Motor Control
Centers as required for air monitors, hand tools, elevators, hoists, heat
trace, etc.
)Q
Safety: Per the original variance, access is permitted by tradespersons tob~
conduct safety-related light carpentry, emergency egress signage installations,
structural shoring as required for safety. No demolition or removals will be
conducted. Approximately four workers will be on site. They will:
1. Install barricades where railings or wall are missing.
2. Re-install two shoring columns that have fallen down.
3. Install no-egress signs on designated doors.
NYC-WTC 000095657
OCR can misread numbers and units. Confirm readings against the page image before using them.