Part V - Quality Assurance Project Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701 - Rev 1 - February 1, 2006
Asbestos 3 3 1 1 4 29
PMio-reference
PM 2.5 Reference
Silica 3 3 1 1 4 29
Dioxins/Furans 3 1 1 1 5 5
PCBs 3 1 1 1 5 5
PAHs 3 1 1 1 5 5
Note 1: Reference sampling for PM-10 and PM-2.5 is being conducted with real-time monitors at one
sampling station for PM-10, and one sampling Station for PM-2.5. Reference location is rotated. No
laboratory samples are processed.
Table 7-2. Abatement Phase: Asbestos and COPC Abatement and Removal Sampling and
Analysis Stininiary
Location Parameter(s) Sample Frequency Analysis Method
Site Aiea Mercury (vapor/gas) Each Day Lumex, portable
mercury analyzer
Site Area Visible dust emissions Each Day Visual observation
Scaffolding/Street 1. Asbestos Each Day (asbestos and silica 1. TEM/PCMe
Level/School Auditorium 2. Silica are sampled during work shift 2.XRD
Roof (3 Locations)
3. Metals Each Day (24 hr. Basis) 3. ICP/MS
4. PCDDs/PCDFs 4. IIRGC/IIRMS
5. PAHs 5. GC/MS
6. PCBs 6. GC/ECD
7. Mercury (total) 7. lodatedCarbon
Trap/CVAFS
8. PMio Continuously “Real-Time” Each 8. EBAM/TEOM
9. PM2.5 Day (PMio and PM2.5 on 24 hour 9. EBAM/TEOM
basis at each location; real-time
TEOM PMio and PM2.5 reference
sampler at 1 location per day on
24- hour basis with location
changed bi-weekly)
Table 7-3. Demolition Phase - Structural Deconstruction Phase Sampling and Analysis
Summary
Location Parameter(s) Sample Frequency Analysis Method
Site Area Mercury (vapor/gas) Each Day Lumex, portable
mercury analyzer
Site Area Visible dust emissions Each Day Visual observation
Scaffolding/Street 1. Asbestos Each Day (asbestos and silica 1. TEM/PCMe
Level/School Auditorium 2. Silica are sampled during work shift 2.XRD
Roof (3 Locations)
31
CITY_21MC100_003239884