NYC-WTC_000449648
Draft QA Plan for ambient air monitoring at 130 Liberty Street deconstruction project, Aug 2005.
76 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗Quality Assurance Project Plan for ambient air monitoring at 130 Liberty Street deconstruction, Aug 2005.
NYC-WTC_000441561–000441677OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
Ambient Air Monitoring Program Section No. 13 Quality Assurance Project Plan Revision No.: 0 130 1 .iberty Street - NY, NY Date: August 2005 Lower Manhattan Development Corporation Page 84 of 116
I’M I (I and PM 2 5 I sing a Reference Sam pier
Tables 13-ld summarizes major maintenance activities for the PMio and PM2.5 samplers. The manufacturer’s documentation should be consulted for a more exhaustive list of maintenance and inspection procedures.
Table 13-ld. Maintenance, Testing, and Inspection Requirement for the Anderson RAAS Sampler Used for FM m and PMi - Acceptance Equipment Frequency/Method Corrective Action Criteria Sampler Dismantle and clean at No obvious Clean or replace inlet/receiver tube manufacturer specified particulate deposits or damaged equipment intervals damage before sampling Power cords Check for crimps or No obvious damage Replace as necessary cracks O-Rings At 3 month intervals, No leaks or Replace as necessary inspect all 0-rings in the compression damage sampler evident Tubing and fittings Visually inspect on No crimps, cracks, or Replace as necessary sample recovery days obstructions; no crossthreading Vacuum pump Replace diaphragm of NA NA vacuum pump annually
• Field QC Flow Check - The field technicians should perform a single point flow check at the normal operating flow rate on a monthly basis. If the results of the field flow check exceed +10% of the flow rate indicated by the sampler, the sampler should be serviced (if necessary) and a new, full multipoint calibration should be performed.
Leak Check - The filter used in the sampler is contained within a cassette. A daily leak check is necessary to demonstrate that the portion of the sample flow rate that leaks past the filter without passing through the filter is insignificant relative to the design flow rate of the sampler. The leak check should be peiTormed at 55 mm Hg vacuum or better. Record the initial vacuum. After ten (10) minutes record the final vacuum. Consult the manufacturer’s documentation to find the acceptable criteria for the difference between the initial and final vacuums. This criteria is sampler dependent as it must take into account the internal volume of the sampler under vacuum.
PM I (I and PM 2 5 Using a Met One E-BAM Continuous Monitor
Maintenance, testing, and inspection requirements for the E-BAM continuous monitors are as follows.
• Audit flow system periodically by performing leak checks and flow audits.
L2005-346 Rev. 1
CITY_21MC100_003243490
NYC-WTC_000441645
OCR can misread numbers and units. Confirm readings against the page image before using them.
Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
NYC-WTC_000449648
Draft QA Plan for ambient air monitoring at 130 Liberty Street deconstruction project, Aug 2005.
76 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000444248
QA plan for ambient air monitoring at 130 Liberty Street deconstruction project, Sept 2005.
75 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000438373
QA plan for ambient air monitoring at 130 Liberty Street deconstruction site, Sept 2005.
75 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000447031
QA plan document for ambient air monitoring program for Liberty Street deconstruction.
73 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000449908
QA plan for ambient air monitoring at 130 Liberty Street deconstruction project, Sept 7, 2005.
73 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000447891
QA plan for ambient air monitoring at 130 Liberty Street, Sept 7, 2005.
73 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000443239
QA plan for ambient air monitoring at 130 Liberty Street deconstruction project, LMDC.
73 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000448520
Quality assurance plan for ambient air monitoring during deconstruction at Liberty Street.
73 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000428324
Draft QA project plan for Ambient Air Monitoring Program at 130 Liberty Street deconstruction (Aug 2005).
74 shared non-person entities · 1 shared topics · similarity 0.999
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000427221
Draft QA Project Plan for ambient air monitoring at 130 Liberty Street deconstruction, TRC scope, Aug 2005.
74 shared non-person entities · 1 shared topics · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000451508
Quality assurance plan for ambient air monitoring at the Liberty Street deconstruction site, Sep 2005.
73 shared non-person entities · 1 shared topics · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000440540
QA Plan document for ambient air monitoring at the 130 Liberty Street deconstruction project, Sept 2005.
73 shared non-person entities · 1 shared topics · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗No available related records indexed in this group.
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
NYC-WTC_000449648
Draft QA Plan for ambient air monitoring at 130 Liberty Street deconstruction project, Aug 2005.
Similarity score 1.000 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000427221
Draft QA Project Plan for ambient air monitoring at 130 Liberty Street deconstruction, TRC scope, Aug 2005.
Similarity score 0.998 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000428324
Draft QA project plan for Ambient Air Monitoring Program at 130 Liberty Street deconstruction (Aug 2005).
Similarity score 0.998 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000451508
Quality assurance plan for ambient air monitoring at the Liberty Street deconstruction site, Sep 2005.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000440540
QA Plan document for ambient air monitoring at the 130 Liberty Street deconstruction project, Sept 2005.
Similarity score 0.992 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000421577
QA plan for ambient air monitoring for the 130 Liberty Street deconstruction project, Sept 2005.
Similarity score 0.991 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Machine-extracted building matches; verify each source. Buildings, never households.
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Draft QA Plan for ambient air monitoring at 130 Liberty Street deconstruction project, Aug 2005.
Similar indexed content
QA plan for ambient air monitoring at 130 Liberty Street deconstruction project, Sept 2005.
Similar indexed content
NYC-WTC_000438373
QA plan for ambient air monitoring at 130 Liberty Street deconstruction site, Sept 2005.
Similar indexed content
QA plan document for ambient air monitoring program for Liberty Street deconstruction.
Similar indexed content
QA plan for ambient air monitoring at 130 Liberty Street deconstruction project, Sept 7, 2005.
Similar indexed content