NYC 9/11 Public Portal Document
Ambient Air Monitoring Program Section No. 7
Qnality Assurance Project Plan Revision No.: 0
130 Liberty Street - NY, NY Date: August 2005
Lower Manhattan Development Corporation Page 31 of 116
Table 7-2. Phase I: Preparation Phase & Asbestos and COPC Abatement and Removal
Sampling and Analysis Summary
Location Parameter(s) Sample Frequency Analysis Method
Site Area Mercury (vapor/gas) Each Day Lumex, portable mercury
analyzer
Site Area Visible dust emissions Each Day Visual observation
Ground/Street 1. Asbestos Each Day (asbestos and 1. TEM/SEM
Level 2. Silica silica are sampled during 2. XRD
(4 Locations) work shift)
3. Metals Each Day (24 hr. Basis) 3. ICP/MS
4. PCDDs/PCDFs 4. HRGC/HRMS
5. PAHs 5. GC/MS
6. PCBs 6. GC/ECD
7. Mercury (total) 7. lodatedCarbon
Trap/eVAFS
8. PMio Continuously “Real-Time” 8. EB AM/Gravimetric
9. PM2.5 Each Day (PMio and PM2.5 9. EB AM/Gravimetric
on 24 hour basis at each
location; PMio and PM2.5
reference sampler at 1
location per day on 24-
hour basis with location
changed monthlv)
Roof Top and 1. Asbestos Each Day (asbestos and 1. TEM/SEM
Scaffolding 2. Silica silica are sampled during 2. XRD
(4 locations on roof work shift)
top and 4 locations 3. Metals Each Day (24 hr. Basis) 3. ICP/MS
on scaffolding) 4. PCDDs/PCDFs 4. HRGC/HRMS
5. PAHs 5. GC/MS
6. PCBs 6. GC/ECD
7. Mercury (total) 7. lodated Carbon
Trap/eVAFS
8. PMio Continuously “Real-Time” 8. EB AM/Gravimetric
9. PM2.5 Each Day (PMio and PM2.5 9. EB AM/Gravimetric
on 24 hour basis at each
location; PMio and PNE ,
reference sampler at 1
location per day on 24-
hour basis with location
changed monthly)
L2005-346 Rev. 1
C ITY_D E P_WO RB Y_C AN N ATA_SU B P_000114672
NYC-WTC_000428355
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000428355Source: NYC Law Department, mirrored locally