NYC 9/11 Public Portal Document
Ambient Air Monitoring Program Section No. 15
Quality Assurance Project Plan Revision No.: 0
130 Liberty Street - NY, NY Date: August 2005
Lower Manhattan Development Corporation Page 106 of 116
• Equipment, instrumentation and supplies kept on reserve,
• Instrument calibration and maintenance,
• Data recording, reduction, review, and reporting, and
• Cleanliness and housekeeping.
Preliminary results of the TSA will be discussed with the Laboratory Manager, Laboratory
Project Manager, and Laboratory QA Manager during a verbal debriefing held at the facility.
Assessment findings will be documented and reported as described in Section 15.2.
Data TSAs
Quarterly data audits will be perfoimed by the TRC Project QA Officer or by a designated
qualified individual. These audits will ensure all calculations are being performed properly for
TEQs, BAP-equivalent concentrations, total PCBs, cumulative averages, etc. These audits will
demonstrate the accuracy of the reported data and eliminate any potential global/systematic
calculation errors.
15.2 Assessment Findings and Corrective Action Responses
The results of the field sampling and fixed laboratory TSAs will be documented in written
reports; in addition, verbal debriefings will also be held at the conclusion of all audits. The
reports will be prepared by the auditor and will describe the scope of the TSA, summarize audit
findings, and recommend corrective action. The report will be distributed to the appropriate
personnel for response: the TRC Field Sampling Coordinator will be responsible for responding
to the field sampling TSA report, and the Laboratory Manager will be responsible for addressing
the fixed laboratory TSA report. Significant issues that are discovered during the TSA and
which could potentially affect data quality or usability will be brought to the immediate attention
of the TRC Project Manager.
The response to the TSA reports will include a description of the corrective action(s) to be
implemented, the identities of the personnel responsible for implementing the corrective action,
and the schedule for implementation/completion. All responses must be completed within two
weeks of issuing the TSA report. The response will be reviewed by the TRC Project QA Officer
and/or TRC Project Manager and, if all issues have been addressed appropriately and in a timely
manner, no further action will be required. In the event that the corrective action(s) are
inadequate or inappropriate, follow-up activities, including additional audits, or discussions with
the TRC Project Manager, will be conducted by the TRC Project QA Officer. The complete
TSA report, including resolution of any deficiencies, will be included in the QA reports to
management.
L2005-346 Rev. 1
C ITY_D E P_WO RB Y_C AN N ATA_SU B P_000114747
NYC-WTC_000428430
OCR can misread numbers and units. Confirm readings against the page image before using them.