Part V - Quality Assurance Project Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701 - September 29, 2005
Cleaning and Deconstruction Work
In September, 2005 the The Greenwich Street Project, LLC released documents for the
Deconstruction of 133-135 Greenwich Street and 21-23 Thames Street buildings.
Deconstruction will include Asbestos and COPC Abatement and Removal and Structural
Deconstruction. The Asbestos and COPC abatement and removal phase includes the
cleaning and removal of all interior surfaces and non-structural elements within the
building under containment. The clean-up and abatement will be conducted so that the
buildings can be safely deconstructed to allow for redevelopment of the Site. The
Asbestos and COPC Abatement and Removal Phase deconstruction will occur while the
work area is placed under negative pressure containment and includes the following
general categories: (a) the general area cleanup of WTC dust and debris, (b) removal and
disposal of installed porous and certain non-porous building materials and components,
(c) cleaning and salvage of certain installed non-porous building equipment
and components, (d) removal of building materials containing asbestos which were
present in the Building prior to September 11th, 2001 (referred to herein as “ACBM”),
primarily within the Building interior, (e) packaging of asbestos and other regulated
waste including, but not limited to light bulbs, lighting ballasts, batteries, mercury-
containing thermostats, etc. at generation points, movement of containers to the
decontamination unit and movement of decontaminated containers to waste loading, and
cleaning of exterior surfaces of the Building (i.e. building washdown). The proposed
cleanup and abatement will be conducted so that the Building can be safely deconstructed
in compliance with applicable law to allow for redevelopment of the Site. Following
Asbestos and COPC Abatement and Removal Phase deconstruction and removal of the
remaining “clean” building components including the clean exterior brick walls, roofs,
and structural wood components will be carried out. The deconstruction of the building at
133-135 Greenwich Street and 21-23 Thames Street is expected to consist generally of:
(a) cleaning and preparation of the building for deconstruction; (b) deconstructing the
building; (c) undertaking environmental monitoring during the deconstruction; (d)
transporting and disposing of all waste and debris from the building; and (e) backfilling,
grading and paving the Site as appropriate following the cleaning and deconstruction.
Regulatory Oversight The The Greenwich Street Project, LLC is the owner of 133-135
Greenwich Street and 21-23 Thames Street and is fully responsible for the cleaning
and deconstruction of the building and will comply with all Federal, State and City
regulations pertaining to environmental protection, asbestos abatement, hazardous
material disposal and construction. The The Greenwich Street Project, LLC released the
draft deconstruction plan documents including Health and Safety Plan, Community
Monitoring Plan, and Waste Characterization Planand Quality Assurance Project Plan in
September, 2005 and formally submitted the plans for review to the following agencies:
• United States Environmental Protection Agency
• United States Occupational Safety and Health Administration (OSHA)
• New York State Department of Labor (NYSDOL)
• New York State Department of Environmental Conservation (NYSDEC)
• New York City Department of Environmental Protection (NYCDEP)