Section 2 - Ambient Air Monitoring Program Revision No.: 0
130 Liberty Street Deconstruction Plan Date: September 7, 2005
Lower Manhattan Development Corporation
project. The proposed cleanup and abatement will be conducted so that the Building can be
safely deconstructed in compliance with applicable law to allow for redevelopment of the WTC
Site.
3.4 Phase II - Structural Deconstruction
Phase II will include the systematic floor-by-floor deconstruction and removal of the remaining
“clean” building components including the clean exterior curtain wall, roof, CMU shafts,
concrete deck, large-scale mechanical equipment components and structural steel components.
Included in Phase II will be the abatement and removal of roof-top asbestos-containing cooling
tower transite materials, rooftop caulking and asbestos-containing caulking found on the
aluminum column covers and fascia. For each specific floor or regulated abatement work area,
all Phase II asbestos abatement work must be completed prior to commencement of any Phase n
floor-by-floor deconstruction for that floor or work area.
3-2
CITY_DEP_WORBY_CANNATA_SUBP_000075882