NYC 9/11 Public Portal Document
Part V - Quality Assurance Project Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701 - September 29, 2005
Trigger Levels for each of the target parameters. A summary listing of the Action Levels
provided on a parameter-specific basis is shown in Table 6-3.
6.3.1 Decisions Based on Project Action Levels The following actions will be taken if
there is an exceedance of any Target Air Quality Level. If there is an exceedance of both
the Target Air Quality Level and USEPA Site Specific Trigger Level, actions associated
with the USEPA Site Specific Trigger Level will govern. In the event that the
deconstruction project is shut down on account of an exceedance of an air quality
action level, monitoring for all parameters will continue. The purpose of the continuation
of monitoring will be to demonstrate that concentrations have been restored to acceptable
levels.
6.3.2 Target Air Quality Levels 6.3.2.1 Definitions of Exceedances Any 24-hour PM2.5
and PMio value in excess of the Target Air Quality Level will be considered an
“exceedance” and the actions described below will be taken. During the first week of
sampling, any sample of an analyte, other than PM2.5 and PMio, in excess of 3 times the
Target Air Quality level for that analyte, unless superseded by a USEPA Site Specific
Trigger Level, will be considered an exceedance and the actions described below will be
taken. Following the first week of sampling, a cumulative average will be established
based initially on the first week’s results, to which will be added daily values as results
are received from the laboratory. A cumulative average value for any analyte other than
PM2.5 and PMio, in excess of the relevant Target Air Quality Level will be considered an
exceedance and the actions described below will be taken.
6.3.2.2 Actions Based on Exceedances Exceedance at any of the twelve (12) monitoring
locations will be handled as set forth in the September 2005 Air Monitoring
Plan. Exceedances of an established Target Air Quality Level for any analyte calculated
as provided above will result in an evaluation of engineering controls and work
techniques in the source area. The evaluation of engineering controls and work
techniques shall determine whether: (i) negative pressure is being maintained in active
work areas at the required levels (ii) there are breaches in the containment in active work
areas, and (iii) there are any visible emissions from the containment areas. In addition,
the evaluation will consider other potential sources contributing to or causing the
exceedance.
6.3.3 USEPA Site Specific Trigger Levels
6.3.3.1 Definition of Exceedances Any 24-hour value (eight-hour value in the case
of asbestos and silica) in excess of the USEPA Site Specific Trigger Level will be
considered an “exceedance” and the actions described below will be taken.
6.3.3.2 Actions Based on Exceedances Exceedance of USEPA Site Specific Trigger
Levels will result in a stoppage of work associated with the exceedance until an
evaluation of emission controls is performed and corrective action is in place. The
USEPA Site Specific Trigger Levels are applicable to individual sample results. If
21
CITY_DEP_WORBY_CANNATA_SUBP_000070955
NYC-WTC_000423905
OCR can misread numbers and units. Confirm readings against the page image before using them.