ALLOWANCE FOR INCIDENTAL ASBESTOS ABATEMENT
16" 12" 4.19
18" 14" 4.71
1.8 METHOD OF PAYMENT
PAYMENT WILL BE MADE AS FOLLOWS, FOR ITEMS A THROUGH 0
BELOW.
A. PIPE INSULATION: Actual linear footage, multiplied by the square footage
factor listed for the respective pipe size in Section 1.07, multiplied by the unit
price in Section 1.5.
EXAMPLE: 100 lin.ft. of 1/2" pipe and 100 lin.ft. of 6" pipe, including elbows,
tees. Flanges, etc.
100 X 0.65 = 65 sq.ft. 65 x unit price = Payment
100 2.62 = 262 sq.ft. 262 x unit price = Payment
B. REMOVAL AND REPLACEMENT OF BOILER INSULATION: (including
Silicate Block) at 2.0 times the unit price per square foot
EXAMPLE: Item B. removal and replacement of 1000 S.F. of boiler insulation
(inch Silicate block)
1000 S.F. X Twice (2X) the Unit Price = Payment
C. REMOVAL AND REPLACEMENT OF TANK INSULATION: (including
Silicate Block) at 2.0 times the unit price per square foot involved.
D. REMOVAL AND REPLACEMENT OF BOILER UPTAKE, &
BREACHING INSULATION: (Including Silicate Block, stiffening angles and
wire lath). At 2.0 times the unit price per square foot involved.
E. REMOVAL AND REPLACEMENT OF DUCT INSULATION: At 2.0 times
the unit price per square foot involved.
F. REMOVAL AND REPLACEMENT OF SOFT ASBESTOS
MATERIAL:(Including sprayed-on fire proofing and soundproofing) at the unit
price per square foot of surface area involved.
G. ACOUSTIC PLASTER REPAIR AND/OR ENCAPSULATION: At 0.5 times
the unit price per square foot involved.
H. ENCLOSURE CONTAINMENT: At 0.7 them the unit price per square foot
involved.
CAPITAL PROJECT NUMBER XXXXX 01020-99
100% CONTRACT DOCUMENTS REV. 0: DATE
CITY_21MC100_006631348
NYC-WTC_000416860