ALLOWANCE FOR INCIDENTAL ASBESTOS ABATEMENT
E. Throughout the specifications, reference is made to codes and standards which
establish qualities and types of workmanship and materials, and which establish
methods for testing and reporting on the pertinent characteristics thereof.
13 WORK ORDER LETTERS
A. Work Order Letters will be issued throughout the Contact period, and as required
to cover the services requested.
1.4 ESTIMATED QUANTITY
The Department of Design and Construction reserves the right during the term of this
Contract to determine the number of Work Order Letters and the Scope of Work to be
included therein, and shall not be deemed to be limited by the estimate amount of the
allowance nor does this Contract guarantee or obligate the Department of Design and
Construction to issue a required number of Work Order Letters. The Contractor is
cautioned that payment will not be made for any work that is not authorized by the
Department of Design and Constimction.
When work is ordered, the Contractor will visit the subject location within one (1)
working day of notification to ascertain actual work required. If the Work Order Letter
identified the project as being "urgent", then work shall commence not later than 48
hours from the time of notification. In this event, the contractor shall immediately notify
EPA NESHAPS Coordinator and NYCDEP of start of the work and file the necessary
Asbestos Variance Application (ACP-9) with the NYCDEP.
In the event that the Work Order Letter does not identify the project as "urgent" the
Contractor shall notify the EPA NESHAPS Coordinator and NYCDEP by letter,
postmarked 10 days before activity begins if 260 linear feet or more and/or 160 square
feet or more of asbestos containing material will be disturbed.
The following information must be included in the notification:
A. Name and address of building City or operator;
B. Project description:
1. Size - square feet, number of linear feet, etc;
2. Age - date of construction and renovations (if known);
3. Use - i.e., office, school, industrial, etc.
4. Scope - repair, demolition, cleaning, etc.
C. Amount of asbestos involved in work and an explanation of techniques used to
determine the amount;
CAPITAL PROJECT NUMBER XXXXX 01020-95
100% CONTRACT DOCUMENTS REV. 0: DATE
CITY_21MC100_006631344
NYC-WTC_000416856