, transaction. The hours in question were added to the next pay period. The
original entry was not backed-out of the project, resulting in double payment.
This error resulted in over billing of $1,674.10 (Exhibit 7).
f. In response to TA’s request to “... provide a clear trail representing all
payroll adjustments and/or corrections.” Safeway submitted explanations that
are inaccurate, demonstrating failure to adequately research Safeway’s in
house documents (Exhibits 7 and 8). For example, in response to TA’s
inquiry, Safeway made an adjustment to its payroll based on a sign-in sheet
produced by Bovis, dated June 14, 2002, where the date in question was June
13, 2002 (Exhibit 9).
At the same time, Safeway referred to its response to Bovis’ inquiry regarding
discrepancies between sign-in sheets and electronic swipe card logs. Safeway
provided an explanation indicating that “Certified payroll confirms that
employee was paid.’’ (Exhibit 10) This response does not address the issue
raised by TA.
g. TA noted instances where Safeway employees were not paid initially due to
the lack of daily logs or swipe card records. In these instances, corrections
were made to the payroll records based solely on Bovis sign-in sheets.
Conversely, TA noted that Bovis sign-in sheets also reflect Safeway
employees who were not invoiced to the project (Exhibit 11). This
demonstrates the lack of integrity in the documentation submitted and
therefore compromises the validity of payroll adjustments.
h. TA noted that Safeway made several corrections to its payroll records.
Several of the payroll conections resulted in other errors. Correction entries
on employees reportedly not paid, were made and in some instances resulted
in the employees being paid twice for the same work performed. Also,
payroll corrections resulting in back-out adjustments appear to be consistently
excluded from the project totals. (Exhibit 12 and 8)
i. Safeway invoiced for clerical services performed at the project site. In
accordance with the DDC policy, (Exhibit 13), clerical services are part of the
Contractor’s overhead. This issue resulted in project over billing in the
amount of $5,538.58 (Exhibit 14).
j. Safeway invoiced for supervisory (other than licensed Asbestos Supervisors)
who, in accordance with DDC’s policy, (Exhibit 12) are part of the
Contractor’s overhead. This resulted in over billing in the amount of
$113,656.19 (Exhibit 15).
k. Through its comparison of licensed personnel invoiced to the project, TA
established that Safeway invoiced for drivers who delivered materials to the
site. Safeway confirmed that the drivers, Adam Koza and Tadeusz Spiewak,
14 07.002952
CONFIDENTIAL INSURANCE INFORMATION, CITY_2IMCl00_003492488
SUBJECT TO PROTECTIVE ORDER NO. 2, SEPT. 2008