NYC 9/11 Public Portal Document
THACHER
ASSOCIATES
SUMMARY OF ANALYSIS
Contract Issues
a) TA’s analysis did not note any documentation or information pertaining to
Contract(s) and or costing Agreement(s) within the submission. Through interviews
with Seasons Contracting and PT&L, TA learned that no written documents defining
the Scope of Work were issued. TA’s review of the supporting documentation and
interviews with Seasons Contracting and PT&L revealed the Scope of Work was
developed through verbal communication as the project events progressed. TA found
no evidence that Seasons Contracting or PT&L received authorization from the site
Health and Safety Contractor (Bechtel) to perform these services. Without contract
or cost agreements it is not possible to evaluate the scope of services, the
authorization dates, or the work execution dates.
b) The analyzed documentation did not contain sampling schedules, directives, requests
for services. Scope of Services or any other information indicating internal or external
controls on service requirements. Without industry standard written procedures, it is
difficult to determine how PT&L performed the services and whether or not the
invoices for the work performed are appropriate.
Integrity Issues
a) The PT&L field data forms, which are identified as “Air Sample Record & Chain of
Custody” include, among other information, the following: unique sample
identification numbers, sample locations, air flow rates, sample start and stop times,
total sample volumes, analytical results, technician identification, method of analysis,
laboratory name and Chain of Custody for sample records. TA’s review of these
forms indicates patterns of data fabrication regarding questionable equipment
calibration (flow rates), sample start and stop times and chain of custody entries.
i. TA identified multiple instances of the same pre-typed flow rates being used
on field data forms where sample start and stop times are hand written. The
start time and initial flow rate are obtained and recorded at the same time as
are the stop time and final flow rate. The repetitive recording of similar data,
day after day, is indicative of fabricated field information. (Attachment 1)
ii. TA identified two (2) types of data fabrication relative to the start and stop
sample times. The first fabrication involved start and end of samples exactly
within five (5) or ten (10) minute intervals (Attachment 2). The second type
of fabrication involved the start and stop times being identical for multiple
sampling locations. Inaccurate time data has a significant impact on the
overall laboratory results. (Attachment 3)
iii. There are several instances when the same data appears to be used; recordings
are exact other than a 12 hour revision to Time on /Time off. All other data
remains identical and, in the case of 11-5/11-6 Chain of Custody forms, the
4
CITY_21MC1OO_O11889777
NYC-WTC_000360846
OCR can misread numbers and units. Confirm readings against the page image before using them.