Contract Issues
a) Through interviews with Seasons Contracting and PT&L, TA learned that there was
no written contract, agreement or directive defining the Scope of Work.
b) TTe materials TA reviewed do not contain sampling schedules, directives, requests
for services. Scope of Services or any other information indicating internal or external
controls on service requirements. Without defined project directives or procedures,
l’A cannot ascertain whether proper control of the monitoring by PT&L at the site
v/as ever performed by Seasons.
Integrity Issues
a) PT&L, through its sub-contractor (Omega Laboratories), generated field data forms
which appear to be fabricated. TA’s analysis of the field data forms identified
numerous discrepancies in the documentation provided.
b) TA, through an interview with PT&L, was told that the Omega Laboratories bill was
resubmitted in the amount of $53,375.26. TA subsequently reviewed the revised
Seasons Contracting/PT&L billings and did not find this reduction in the Omega
Laboratories portion of the revised bill.
c) TA’s findings also indicate that, on numerous occasions, proper Chain-of-Custody
procedures were not followed. Examples include missing or incomplete information
Ln the Chain-of-Custody section of the field data forms.
d) Field data forms for bulk samples were submitted with indications of “field blanks.”
ITiere are no field blanks required with any bulk sample procedure.
Billing issues
a) TA identified excessive billing by PT&L through their sub-contractor, Omega
Laboratories. Thus excessive billing was a result of Omega Laboratories utilizing
twice the number of technical field personnel to perform the sampling function. The
potential overcharge of the project overstaffing is $53,400.00.
b) TA identified over billing by PT&L for its sub-contractors, Omega Laboratories,
Eastern Analytical Services, Galson Laboratories, JLC Environmental Consultants
snd USX Engineers & Consultants, Inc. This over billing was a result of PT&L
charging overhead and profit at a rate of 21%, billing the sub-contractors as materials,
as opposed to 5% as “other tier” contractors. The potential overcharge is $23,585.01
c) Excessive field blanks and lot blanks were submitted to inflate the cost of laboratoiy
analytical services. Due to the volume of material and discrepancies identified within
support documentation provided, TA is of the opinion that cost savings analysis is
cost prohibitive.