[ Jessica Leighton - RA_sitrepO1-25.wpci Page 3
NYC / ER (Jan 19 -21) - Asbestos Monitoring (Particulate Monitoring Stations)
o Monitoring sites include:
ParkRpw (Site 1)
Chambers St./West St. (Site 2)
Public School 154: 333 East 135”^ St, Bronx (Site 5)
Intermediate School 143: 511 West 182— St., Manhattan (Site 6)
Public School 274: 800 Bushwick Ave., Brooklyn (Site 7)
Public School 44: 80 Maple Parkway, Staten Island (Site 8)
Public School 199: 3290 - 48- Ave., Queens (Site 9)
o During this period a total of 20 samples were collected from these monitoring sites.
o All of the samples were below the TEM AHERA standard.
NYC / ER (Jan 23) - Particulate Monitoring (Dataram)
o No particulate measurements were conducted at Stations L, N, and R due to the
weather conditions.
NYC / ER (Jan 24) - Volatile Organics (Mobile Laboratory)
o Benzene was not detected above the detection limit (20 ppbv) in any of the four
samples collected (Washing Tent, Austin Tobin Plaza, North Tower, and South
Tower), including in the debris area at ground level.
o A limited number (3) of VOCs were detected above the detection limit (20 ppbv) in
only the North Tower groimd level samples.